Home › Capital works › 2026–2029
Capital Works Program 2026–2029
Transport And Traffic — total $216M
Road Safety and Operations
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bannerman Street Footpath Installation of a new footpath on Bannerman Street, between Becker Street and Riverview State School, Riverview. | ● | PDF p.2 ↗ | |||
| Haigslea Amberley Road Footpath Installation of a new footpath for a missing link on Haigslea Amberley Road, along the property frontage of Walloon State School, Walloon. | ● | PDF p.2 ↗ | |||
| iGO Intelligent Transport Systems Strategy Implementation Implementation of the iGO Intelligent Transport Systems Strategy citywide improvements to council's road based technology. | ● | ● | ● | PDF p.2 ↗ | |
| iGO Road Safety Action Plan Implementation Implementation of the iGO Road Safety Action Plan citywide safety improvements to council's road network. | ● | ● | ● | PDF p.2 ↗ | |
| Lobb Street Guardrail Installation of guardrail at the steep embankment on Lobb Street, Churchill. | ● | PDF p.2 ↗ | |||
| Lobb Street Road Safety Improvements Implementation of road safety improvements along Lobb Street, near the intersection at Perry Street, Churchill. | ● | PDF p.2 ↗ | |||
| Minor Improvements – Road Safety and Operations Reactive, citywide, minor safety and operational improvements to council's transport network. Projects are typically identified through the service request process or routine inspections. | ● | ● | ● | PDF p.2 ↗ | |
| Refuse Vehicle Turnaround Facilities Upgrade to existing turnaround facilities to accommodate refuse vehicles and eliminate the need for reversing. | ● | ● | ● | PDF p.3 ↗ | |
| Regents Drive Road Safety Improvements Pedestrian safety improvements, including fencing, on Regents Drive near Fernbrooke State School, Redbank Plains. | ● | PDF p.3 ↗ | |||
| Road Safety and Operations Projects Road safety and operations projects implemented as a result of road safety audit recommendations. | ● | ● | PDF p.3 ↗ | ||
| Road Safety Concept Design Conceptual design for future strategic road improvement and upgrade projects. | ● | ● | ● | PDF p.3 ↗ | |
| Signs and Lines Unallocated citywide budget focused on reactive signage and line marking requests that are generally received by the service request process. | ● | ● | ● | PDF p.3 ↗ | |
| Stuart Street and Bellevue Road Footpath Installation of a new footpath on Stuart Street and Bellevue Road, Goodna. | ● | PDF p.3 ↗ | |||
| Traffic Signal Modifications and Improvements Unallocated budget is used for reactive and unplanned citywide traffic signal improvements. | ● | ● | ● | PDF p.3 ↗ | |
| Wandera Court Footpath Installation of a new footpath on Wandera Court, between Wandera Court to Redbank Plains State School, Redbank Plains. | ● | PDF p.3 ↗ | |||
| Road Safety and Operations Total | $2.8M | $1.1M | $1.5M | $5.4M |
Strategic Transport
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Augusta Parkway and Sinnathamby Boulevard Road Upgrade Upgrade of Augusta Parkway and Sinnathamby Boulevard, to a standard of a four-lane urban road from Eden Station Drive to Main Street, including a bridge duplication, Springfield Central/Augustine Heights. | ● | ● | ● | PDF p.3 ↗ | |
| Blackstone Road, Thomas and Creek Streets Intersection Upgrade Upgrade of the intersection at Blackstone Road, Thomas Street and Creek Street to a roundabout, Silkstone. | ● | ● | ● | PDF p.3 ↗ | |
| Corridor Planning and Concept Design Work Corridor planning and early concept design work for iGO identified projects. | ● | PDF p.3 ↗ | |||
| Eden Station Drive and Northern Sports Fields Intersection Upgrade Upgrade of the intersection at Eden Station Drive and Northern Sports Fields Access to a signalised intersection, Springfield Central. | ● | ● | PDF p.3 ↗ | ||
| Fischer Road Upgrade Upgrade of Fischer Road from Nevis Road to Monterea Road to a two-lane urban road standard, Ripley. | ● | ● | ● | PDF p.3 ↗ | |
| Hooper, Moffatt and Pound Streets Intersection Upgrade Upgrade of the intersection at Hooper Street, Moffatt Street and Pound Street, West Ipswich. | ● | ● | ● | PDF p.3 ↗ | |
| Redbank Plains Road Upgrade Stage 3B Upgrade of Redbank Plains Road, to a standard of a four-lane urban road, extending from Keidges Road to Kruger Parade, Bellbird Park/ Redbank Plains. | ● | ● | ● | PDF p.3 ↗ | |
| Redbank Plains Road Upgrade Stage 4 Upgrade of Redbank Plains Road, to a standard of a four-lane urban road, extending from Collingwood Drive, Collingwood Park/Redbank Plains, to the Cunningham Highway, New Chum/Swanbank. | ● | ● | ● | PDF p.3 ↗ | |
| Ripley Road and Reif Street Intersection Upgrade Upgrade of the intersection at Ripley Road and Reif Street, Flinders View. | ● | PDF p.3 ↗ | |||
| Ripley Road Upgrade Stage 1 Upgrade of Ripley Road, to a standard of a four-lane urban road from Cunningham Highway to Monterea Road, Ripley. | ● | ● | PDF p.3 ↗ | ||
| Ripley Road Upgrade Stage 2 Upgrade of Ripley Road, to a standard of a four-lane urban road from Monterea Road to Fischer Road, Ripley. | ● | ● | ● | PDF p.3 ↗ | |
| School Road Upgrade Upgrade of School Road, to a standard of a four-lane urban road, extending from Redbank Plains Road to Alawoona Street, Redbank Plains. | ● | ● | ● | PDF p.3 ↗ | |
| Springfield Parkway Road Upgrade Stage 2 Upgrade of Springfield Parkway, to a standard of a four-lane urban road, extending from Topaz Road to Hymba Yumba Independent School, Springfield. | ● | ● | ● | PDF p.4 ↗ | |
| Toongarra Road Upgrade Upgrade of Toongarra Road, to a standard of a four-lane urban road, extending from Old Toowoomba Road to Samford Road, Leichhardt. | ● | PDF p.4 ↗ | |||
| Strategic Transport Total | $59M | $77.3M | $62.9M | $199.2M |
Sustainable Travel
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bremer Street Footpath Stage 2 Installation of a new shared path on the northern verge of Bremer Street, from Bell Street to Ellenborough Street, Ipswich. | ● | PDF p.4 ↗ | |||
| Cycle Safety and Mobility Improvement Program Small scale projects to improve accessibility or safety to existing bicycle infrastructure and missing links in the cycle network. | ● | ● | ● | PDF p.4 ↗ | |
| Eastern Ipswich Link Bikeway Stage 3 Installation of a commuter bikeway along Glebe Road from the corner of Chermside Road and Brisbane Road, Ipswich to South Station Road, Booval. | ● | PDF p.4 ↗ | |||
| Goodna Creek Bikeway Stage 4 Installation of a bikeway along Goodna Creek, connecting Farmer Court, Redbank Plains to Woodlinks Village Estate, Collingwood Park. | ● | ● | PDF p.4 ↗ | ||
| Goodna Town Centre Active Transport Action Plan (ATAP) Pedestrian Improvements Improvements to pedestrian facilities within the walking catchment of the Goodna Town Centre, Goodna. | ● | PDF p.4 ↗ | |||
| Hunter Street ATAP Kerb Ramps Improvements Kerb ramp improvements at intersection of Hunter Street and Workshops Street, Brassall. | ● | ● | PDF p.4 ↗ | ||
| iGO Public Transport Action Plan Public transport upgrade projects prioritising community-identified safety, security, amenity and accessibility issues, aligning with the iGO Public Transport Advocacy and Action Plan. Projects may include bus stop shelter or seat, safety improvement and footpath connection to bus stops. | ● | ● | ● | PDF p.4 ↗ | |
| Ipswich City Centre Bikeway Stage 1 Installation of a commuter bikeway from the intersection of Thorn Street and South Street to East Street and South Street, Ipswich. | ● | PDF p.4 ↗ | |||
| Ipswich City Centre Bikeway Stage 2 Installation of a commuter bikeway from the intersection of South Street and Nicholas Street to Roderick Street and Omar Street along Limestone Street, Ipswich. | ● | PDF p.4 ↗ | |||
| Keidges Road ATAP Footpath Installation of a footpath, kerb ramps, tree planting and landscaping on the western verge of Keidges Road between Lillian Street and Cudgee Street, Redbank Plains. | ● | PDF p.4 ↗ | |||
| Marsden Parade (Gordon Street) Footpath Pedestrian link through the existing Queensland Rail underpass on Gordon Street, Ipswich. | ● | PDF p.4 ↗ | |||
| Pedestrian Safety Improvements Reactive pedestrian safety improvement projects identified through council's internal and external service request process. | ● | ● | ● | PDF p.4 ↗ | |
| Public Transport Disability Improvement Program Upgrades to existing bus stops to comply with current legislative requirements. | ● | ● | ● | PDF p.4 ↗ | |
| Riverlink Bus Station ATAP Pedestrian Improvements Improvements to pedestrian facilities within the walking catchment of the Riverlink Bus Station, excluding works within the Riverlink Shopping Centre, North Ipswich. | ● | ● | PDF p.4 ↗ | ||
| Springfield Lakes Boulevard ATAP Pedestrian Refuge Installation of a pedestrian refuge island on Springfield Lakes Boulevard at the western leg of the Springfield Lakes Boulevard and Burlington Terrace roundabout, Springfield Lakes. | ● | ● | PDF p.4 ↗ | ||
| Summit Drive ATAP Crossing North Installation of a pedestrian crossing facility on the northern end of Summit Drive at the intersection with Springfield Lakes Boulevard, prioritising the active transport connection between the school and shops, Springfield Lakes. | ● | ● | PDF p.4 ↗ | ||
| Summit Drive ATAP Crossing South Pedestrian crossing improvements at the roundabout of Summit Drive and Springfield Lakes Boulevard near the Atlantic Drive Sporting Complex, Springfield Lakes. | ● | ● | PDF p.4 ↗ | ||
| Sustainable Travel Forward Design Forward design for future projects within the Sustainable Travel program. | ● | PDF p.5 ↗ | |||
| West Street ATAP Footpath Installation of a footpath on the eastern side of Redbank Plains Recreational Reserve between the Redbank Plains State High School and existing footpath in West Street, Redbank Plains. | ● | ● | PDF p.5 ↗ | ||
| Willow Road ATAP Footpath Stage 1 Installation of a footpath and landscaping on the southern verge of Willow Road, between 123–127 Willow Road and Keidges Road, Redbank Plains. | ● | PDF p.5 ↗ | |||
| Willow Road ATAP Footpath Stage 2 Improvements to the footpath and landscaping on the northern verge of Willow Road, between the Goodna Creek Bikeway and Keidges Road, Redbank Plains. | ● | ● | PDF p.5 ↗ | ||
| Workshops Street ATAP Footpath Installation of a footpath on southern side of Workshops Street, between Hunter Street and Vogel Road, Brassall. | ● | ● | PDF p.5 ↗ | ||
| Sustainable Travel Total | $4.4M | $3.5M | $3.6M | $11.5M |
Flood Mitigation And Drainage — total $5.7M
Flood Mitigation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Citywide Flood Impact Design Preliminary design of flooding hotspots identified across the city. | ● | ● | ● | PDF p.5 ↗ | |
| Marburg Detention Basin Upgrade Upgrade of the Marburg detention basin to meet flood capacity requirements, Marburg. | ● | ● | PDF p.5 ↗ | ||
| Flood Mitigation Total | $1.6M | $1.6M | $100k | $3.3M |
Local Drainage
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Annual Local Drainage Projects Unallocated citywide budget for planning, design and construction of stormwater drainage infrastructure in flooding hotspots. | ● | ● | PDF p.5 ↗ | ||
| Bellbird Park Stormwater Drainage Improvements Upgrade of existing stormwater drainage network on Perdita Street, Katandra Court and Rosemary Street, Bellbird Park. | ● | PDF p.5 ↗ | |||
| Minor Stormwater Drainage Improvement Projects Undertake minor stormwater drainage improvements based on reactive requirements from service requests. | ● | ● | ● | PDF p.5 ↗ | |
| Parcell and Holt Street Drainage Improvements Improvements to the existing stormwater drainage adjacent to Parcell Street and Holt Street, Brassall. | ● | PDF p.5 ↗ | |||
| Local Drainage Total | $1.2M | $560k | $560k | $2.4M |
Parks And Recreation — total $11M
New Parks and Recreation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Developer Funded Parks Projects Unidentified developer funded parks projects. | ● | ● | PDF p.5 ↗ | ||
| Goupong Park Facilities and Equipment Upgrade Upgrade of the facilities and playground equipment at Goupong Park, Collingwood Park. | ● | ● | ● | PDF p.5 ↗ | |
| Public Recreation Parks Program Planning, design and construction of citywide priority public recreation parks. | ● | ● | PDF p.5 ↗ | ||
| New Parks and Recreation Total | $30k | $600k | $2.6M | $3.2M |
Parks and Recreation Upgrades
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Compliance, Safety and Improvements to Local Parks Budget allocation is for minor compliance or safety improvements to council's assets based on inspections and service requests within Local Parks. | ● | ● | ● | PDF p.6 ↗ | |
| Compliance, Safety and Improvements to Strategic Parks Budget allocation is for minor compliance or safety improvements to council's assets based on inspections and service requests within Strategic Parks. | ● | ● | ● | PDF p.6 ↗ | |
| Kholo Gardens New Retaining Wall Installation of a retaining wall to protect the embankment and historic brick water wells in Kholo Gardens, Muirlea. | ● | ● | ● | PDF p.6 ↗ | |
| Limestone Park Fitness Equipment Upgrade Upgrade of the existing fitness equipment at Limestone Park, Ipswich. | ● | PDF p.6 ↗ | |||
| Limestone Park Fitness Shade Structure Installation Installation of a shade structure for the fitness equipment at Limestone Park, Ipswich. | ● | PDF p.6 ↗ | |||
| Limestone Park New Amenities Installation of new amenities facility within Limestone Park, Ipswich. | ● | ● | PDF p.6 ↗ | ||
| Limestone Park New Dog Off Leash Area Installation of new dog off leash area in Limestone Park, Ipswich. | ● | PDF p.6 ↗ | |||
| Local and District Park Amenities Accessibility Improvements Accessibility improvements to toilets within local and district parks. | ● | ● | PDF p.6 ↗ | ||
| Nerima Gardens Upgrade Upgrade works to the Nerima Gardens, Ipswich. | ● | ● | PDF p.6 ↗ | ||
| Park Fencing and Bollard Projects Provide fencing and bollards to various parks across the city. | ● | ● | ● | PDF p.6 ↗ | |
| Parks Fitness Equipment Program Unallocated citywide budget for new or upgrades to fitness equipment. | ● | PDF p.6 ↗ | |||
| Queens Park Playground Upgrade Upgrade to the existing playground within Queens Park, Ipswich. | ● | ● | ● | PDF p.6 ↗ | |
| Skate and BMX Facilities Program Unallocated citywide budget for new or upgrades to skate and BMX facilities. | ● | PDF p.6 ↗ | |||
| Spring Lake Park New Amenities Installation of a new toilet at Spring Lake Park adjacent to Montello Circuit, Springfield Lakes. | ● | ● | PDF p.6 ↗ | ||
| Upgrade of Existing Leash Free Dog Areas Upgrades of existing leash free dog areas. | ● | PDF p.6 ↗ | |||
| Parks and Recreation Upgrades Total | $1.5M | $2.9M | $3.4M | $7.7M |
Sports Facilities — total $65.6M
New Sporting Facilities
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| DA22B Sports Facility Council's contribution towards the development of the DA22B Sports Facility, Springfield Central. | ● | PDF p.6 ↗ | |||
| Redbank Plains Recreation Reserve New Clubhouse and Amenities Installation of a clubhouse and amenities block at the Redbank Plains Recreation Reserve, Redbank Plains (change rooms and amenities component of clubhouse). | ● | ● | ● | PDF p.6 ↗ | |
| Redbank Plains Recreation Reserve New Sports Facility Installation of new sports fields, back netting, car park, connecting pathways and future provision for a clubhouse within Redbank Plains Recreation Reserve, Redbank Plains. | ● | PDF p.6 ↗ | |||
| Redbank Plains Recreation Reserve New Sports Field Development of third rectangular field and oval with lights, irrigation and connection road to Willow Road, Redbank Plains. | ● | PDF p.6 ↗ | |||
| Regional Sports Hub Stage 1 A regional level facility to accommodate growth for sport and recreation. | ● | PDF p.6 ↗ | |||
| Regional Sports Hub Stage 2 A regional level facility to accommodate growth for sport and recreation. | ● | PDF p.6 ↗ | |||
| Tivoli Sporting Complex Baseball Diamond A Lighting New sports field lighting for Baseball Diamond A at Tivoli Sporting Complex, Tivoli. | ● | ● | PDF p.6 ↗ | ||
| Tivoli Sporting Complex New Amenities Installation of an amenities facility at Tivoli Sporting Complex, Tivoli. | ● | PDF p.6 ↗ | |||
| New Sporting Facilities Total | $14.1M | $27.6M | $1.4M | $43.1M |
Sports Facilities Upgrades
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Andre Ripoll Park Toilet Upgrade Upgrade existing public toilet from one cubicle to three cubicles for public and club to meet capacity and demand. | ● | ● | PDF p.7 ↗ | ||
| Caledonian Park Amenities Upgrade Construction of upgraded amenity facility at Caledonian Park, Thagoona. | ● | PDF p.7 ↗ | |||
| Centenary Sports Facility Upgrade Installation of cricket practice nets, AFL goal posts, dugouts, scoreboard, sight screens and back netting at Centenary Sports Field, South Ripley. | ● | ● | PDF p.7 ↗ | ||
| Citywide Athletics Running Track A new synthetic athletics track at a suitable Ipswich City Council sporting facility. | ● | ● | PDF p.7 ↗ | ||
| Evan Marginson Park Irrigation Upgrade Irrigation upgrade to the sports fields in Evan Marginson Park, Goodna. | ● | ● | PDF p.7 ↗ | ||
| George and Eileen Hastings Sports Centre Diamond 4 Lighting Design and construction of sports field lighting to Diamond 4 for competition standards. | ● | PDF p.7 ↗ | |||
| George and Eileen Hastings Sporting Complex New Amenities Installation of an amenities facility at the George and Eileen Hastings Sporting Complex, One Mile. | ● | PDF p.7 ↗ | |||
| Ipswich Motorsport Precinct Lease A Switchboard Upgrade Upgrade of existing Electrical Switchboard on Lease A to meet current users and future developments. Current switchboard is at capacity. | ● | ● | PDF p.7 ↗ | ||
| Ironbark Park Sports Facility Upgrade Installation of additional goal posts, back netting, dugouts, shelters and seating at Ironbark Park, South Ripley. | ● | ● | PDF p.7 ↗ | ||
| Jim Donald Parklands Sports Field Nets Installation of back netting to sports fields at Jim Donald Parklands, Silkstone. | ● | PDF p.7 ↗ | |||
| Limestone Park Car Park Extension Upgrade of existing gravel car park near the netball courts in Limestone Park, Ipswich. | ● | ● | PDF p.7 ↗ | ||
| Limestone Park Top Car Park Lighting Stage 2 Installation of new car park lighting to the Whyte Family Clubhouse, Ipswich. | ● | PDF p.7 ↗ | |||
| North Ipswich Sport and Entertainment Precinct Upgrade and Expansion Upgrade works to the North Ipswich Sport and Entertainment Precinct identified as part of the master plan. | ● | ● | PDF p.7 ↗ | ||
| Queens Park Bowls Club Amenities and Greens Access Improvements DDA toilet, lift and access ramp to greens to improve accessibility. | ● | ● | PDF p.7 ↗ | ||
| Queens Park Tennis Centre Court Surface and Fence Replacement Installation of synthetic grass and fencing replacement at Queens Park Tennis Centre, Ipswich. | ● | PDF p.7 ↗ | |||
| Redbank Plains Recreation Reserve Cricket Net Lighting Installation of cricket net lighting at Redbank Plains Recreation Reserve, Redbank Plains. | ● | PDF p.7 ↗ | |||
| Redbank Plains Recreation Reserve Entrance Development of entrance to Redbank Plains Recreation Reserve at the intersection of Redbank Plains Road and Henty Drive, Redbank Plains. | ● | PDF p.7 ↗ | |||
| Redbank Plains Recreation Reserve Internal Road Lighting Installation of additional street lighting within the Redbank Plains Recreation Reserve, Redbank Plains. | ● | ● | PDF p.7 ↗ | ||
| Sports Centre (Ripley Valley) Plan, design and construct sports centre and clubhouse. | ● | ● | ● | PDF p.7 ↗ | |
| Springfield Central Sports Complex Cricket Net Lighting Installation of cricket net lighting at Springfield Central Sports Complex, Springfield Central. | ● | PDF p.7 ↗ | |||
| Tivoli Sporting Complex Car Park, Internal Road and Footpath Lighting Design and construction of car park, internal road and footpath lighting at Tivoli Sporting Complex, Tivoli. | ● | ● | PDF p.7 ↗ | ||
| Tivoli Sporting Complex Clubhouse Installation of a new clubhouse to be located within the Tivoli Sporting Complex, Tivoli. | ● | ● | ● | PDF p.7 ↗ | |
| Tivoli Sporting Complex Upgrade Expansion of the existing Tivoli Sporting Complex, Tivoli. | ● | PDF p.7 ↗ | |||
| Various Compliance, Safety and Improvements to all Sporting Facilities Minor compliance or safety improvements to council's assets based on inspections and service requests within sports facilities. | ● | ● | PDF p.7 ↗ | ||
| Various Sporting Facilities Amenities Accessibility Improvements Unallocated citywide budget for accessibility improvements to toilets within sports parks facilities. | ● | ● | PDF p.8 ↗ | ||
| Various Sporting Facilities Fencing and Bollard Projects Provide fencing and bollards to various sporting facilities across the city. | ● | ● | PDF p.8 ↗ | ||
| Various Sporting Facilities Pathway Lighting Projects Provide pathway lighting to various sporting facilities across the city. Includes security and car park lighting. | ● | ● | PDF p.8 ↗ | ||
| Various Sporting Facilities Pathway Projects Unallocated citywide budget to provide accessible concrete pathways in various sporting facilities across the city. | ● | ● | PDF p.8 ↗ | ||
| Various Sports Infrastructure Program Unallocated citywide budget for planning, design and construction of sports infrastructure. | ● | PDF p.8 ↗ | |||
| Various Unallocated Preliminary Design Works for Sport Facilities Unallocated preliminary design budget for sport facility projects. | ● | PDF p.8 ↗ | |||
| White Rock Local Sports Park Sports Facility Upgrade Installation of additional goal posts, back netting, dugouts, shelters and seating at White Rock Sports Park, South Ripley. | ● | PDF p.8 ↗ | |||
| Sports Facilities Upgrades Total | $9.9M | $6M | $5.9M | $21.8M |
Sport and Recreation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Smart Lighting for sports fields and courts Unallocated citywide budget for planning, design and construction of smart lighting for sports fields and courts. | ● | ● | ● | PDF p.8 ↗ | |
| Sports facilities – minor works – New Capital Unallocated citywide budget for planning, design and construction of new minor works at sports facilities. | ● | ● | ● | PDF p.8 ↗ | |
| Sports facilities – minor works – Refurbishment Unallocated citywide budget for planning, design and construction of minor sports facilities refurbishment works. | ● | ● | ● | PDF p.8 ↗ | |
| Sport and Recreation Total | $210k | $220k | $220k | $650k |
Environment — total $23M
Enviroplan
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Enviroplan Improvements to Conservation Estates and Reserves. Projects vary from signage, to trail upgrades and fencing. | ● | PDF p.8 ↗ | |||
| Flinders-Goolman Conservation Estate Entrance Upgrade Upgrade to the Mount Elliot Road entry/gates, fencing, sign and track works. | ● | PDF p.8 ↗ | |||
| Flinders-Goolman Conservation Estate Track Upgrades Central Ridge Track renewal and upgrade vehicle tracks (approximately 2,000m). Ellison Road renewal and upgrade vehicle tracks (approximately 2,000m). Honeymoon Hill Track renewal and upgrade vehicle tracks (approximately 2,000m). Install new service trail (approximately 1,000m) from newly acquired block on Ellison Road to Harding's Paddock. Mount Blaine Track renewal and major upgrade (approximately 2,000m). Spotted Gum/Flinders - Goolman hiking trail major erosion reconstruction. Upgrade of the Gamlen Circuit (Western) section. | ● | PDF p.8 ↗ | |||
| Haig Street Quarry Conservation Reserve Facilities Upgrade Quarry Day Use upgrade, info bay, gardens and slip rail. | ● | PDF p.9 ↗ | |||
| Haig Street Quarry Conservation Reserve Fencing 200m Fencing North/western boundary. | ● | PDF p.9 ↗ | |||
| Haig Street Quarry Conservation Reserve Track Upgrades Renew and upgrade (1,000m) of the Willy Wag Tail Circuit. | ● | PDF p.9 ↗ | |||
| Mount Grandchester Conservation Estate Fencing Install new rural fencing (900m) along the southern boundary of the Estate. | ● | PDF p.9 ↗ | |||
| Paperbark Flats Day Use Area Upgrade The upgrade to Paper Bark Flats Day Use Area will deliver a high standard amenity that enhances visitor experience to the estate while celebrating the natural character and cultural heritage of the area. | ● | ● | ● | PDF p.9 ↗ | |
| Purga Nature Reserve Fencing Install new fencing (120m) and farm gate along the front boundary of the Reserve along Middle Road, Purga. | ● | PDF p.9 ↗ | |||
| Redbank Rifle Range Track Upgrade Upgrade of the Redbank Rifle Range Northern Track section. | ● | PDF p.9 ↗ | |||
| Various Minor Emergent Projects Minor emergent projects. | ● | ● | PDF p.9 ↗ | ||
| White Rock - Spring Mountain Conservation Estate Fencing Archery Range Track fencing. Iron Bark Track fencing. | ● | PDF p.9 ↗ | |||
| White Rock - Spring Mountain Conservation Estate Track Upgrades Archery Range Track upgrade. Iron Bark Track upgrade. Major renewal and upgrade of the Powerlink Track from Paperbark Flats to Haul Road. Upgrade (approximately 2,700m) section of Spring Mountain Trail from Spring Mountain to Woogaroo Creek junction. Upgrade of the White Rock Loop Track. Upgrade of the White Rock Track from Paperbark Flats Day Use Area to White Rock (3,500m). | ● | PDF p.9 ↗ | |||
| White Rock - Spring Mountain Conservation Estate Wayfinding Signage Install of wayfinding signage. | ● | ● | PDF p.9 ↗ | ||
| Enviroplan Total | $2.7M | $1.8M | $2.1M | $6.5M |
Ipswich Nature Centre
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Ipswich Nature Centre Biosecurity Upgrade Major upgrade of biosecurity area. | ● | ● | PDF p.9 ↗ | ||
| Ipswich Nature Centre Improvements Minor improvements to the Ipswich Nature Centre within Queens Park, Ipswich. | ● | ● | ● | PDF p.9 ↗ | |
| Ipswich Nature Centre Total | $1.9M | $2.1M | $52k | $4.1M |
Natural Environment and Stormwater
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bremervale Park Constructed Wetlands Upgrade Installation of a new ephemeral wetlands at Bremervale Park, Raceview. | ● | PDF p.9 ↗ | |||
| Brenda Court Stormwater Quality Improvement Installation of stormwater quality improvement at Brenda Court, Collingwood Park. | ● | ● | PDF p.9 ↗ | ||
| Grace Street Channel Naturalisation Installation of ephemeral wetlands and channel naturalisation adjacent Grace Street, Wulkuraka. | ● | ● | PDF p.10 ↗ | ||
| Heit Family Park Wetlands and Naturalisation Installation of ephemeral wetlands and channel naturalisation at Heit Family Park, Willowbank. | ● | ● | PDF p.10 ↗ | ||
| Local Bushland Reserve Improvements Improvements to existing bushland reserves across the city including upgrades to tracks/ access, installation of bike deterrents and fencing and signage. | ● | ● | ● | PDF p.10 ↗ | |
| Sarah Drive Park Bioretention Basin Rectification Works Rectification works at the recently constructed bioretention basin at Sarah Drive Park, Yamanto. | ● | ● | ● | PDF p.10 ↗ | |
| Natural Environment and Stormwater Total | $2.1M | $2.3M | $1.1M | $5.5M |
Ti Tree Bioenergy Funded
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Armstrong Park Fencing Upgrade Boundary fence modification and slide rail installation at Armstrong Park, Rosewood. | ● | PDF p.10 ↗ | |||
| Caledonian Park Amenities Upgrade Detailed design for upgraded amenity facility at Caledonian Park, Thagoona. | ● | PDF p.10 ↗ | |||
| Coopers Road Footpath Footpath, kerb and channel installation on Coopers Road, from the corner of Cunningham Highway to Willowbank Drive, Willowbank. | ● | PDF p.10 ↗ | |||
| Paynes Road Koala and Community Reserve Establishment of a koala and community reserve at Paynes Road, Ebenezer. | ● | ● | ● | PDF p.10 ↗ | |
| Thagoona Fencing Boundary fences (north and south) at Pindari Drive Reserve, Thagoona. | ● | PDF p.10 ↗ | |||
| Ti Tree Projects Ti Tree Bioenergy funds are to be utilised expressly for the purposes of community and environmental benefit and to offset any impacts from the facility. | ● | ● | ● | PDF p.10 ↗ | |
| Willowbank Playground Upgrade Accessible entries, additional play equipment and play equipment upgrades. | ● | PDF p.10 ↗ | |||
| Ti Tree Bioenergy Funded Total | $2.3M | $1M | $1M | $4.3M |
Waterway Recovery
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bremer River Bank Stabilisation Stage 1 Rehabilitation of eroded streambanks in the Brisbane River, following the February 2022 flood events. | ● | PDF p.10 ↗ | |||
| Bremer River Streambank Rehabilitation Rehabilitation of eroded streambanks in the Bremer River, following the February 2022 flood events. | ● | PDF p.10 ↗ | |||
| Bremer River V-Notch Gauging Weir Fish Barrier Remediation Remediation works to a priority fish barrier in the Bremer River at Walloon to restore connectivity. | ● | ● | PDF p.10 ↗ | ||
| Kholo Bridge Reserve Launch and Access Point Formalisation of a paddle craft access point to the Brisbane River at Kholo Bridge, Muirlea. | ● | ● | ● | PDF p.10 ↗ | |
| Warrill Creek Fish Barrier Remediation Remediation works to a priority fish barrier in Warrill Creek at Purga to restore connectivity. | ● | ● | ● | PDF p.10 ↗ | |
| Waterway Recovery Projects Unallocated citywide budget for planning, design and construction of waterway recovery projects. | ● | PDF p.10 ↗ | |||
| Woogaroo Creek Stabilisation Stage 6 Rehabilitation of eroded streambanks in the Woogaroo Creek, following the February 2022 flood events. | ● | ● | PDF p.10 ↗ | ||
| Waterway Recovery Total | $950k | $505k | $1.1M | $2.6M |
Local Amenity — total $19.4M
Ipswich Central Revitalisation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Brisbane Street Light Up Ipswich Central Installation of fairy lights in the fig trees on Brisbane Street, Ipswich. | ● | PDF p.11 ↗ | |||
| Brisbane Street Top of Town Refresh Upgrade and refurbishment to the existing streetscape at the top of town, on Brisbane Street, Ipswich. | ● | ● | ● | PDF p.11 ↗ | |
| Ipswich Central Revitalisation Revitalisation projects within Ipswich Central, focusing on walkability, place movement and connectivity, Ipswich. | ● | ● | ● | PDF p.11 ↗ | |
| Limestone Street and Gordon Street Green Urban Infrastructure Upgrade the existing footpath on Limestone Street and Gordon Street to support the city's cultural assets, walkability and accessibility, Ipswich. | ● | ● | PDF p.11 ↗ | ||
| Nicholas Street Cultural Heart Stage 1 and 2 Creation of a green and connected spine between d'Arcy Doyle Place and South Street to support the city's cultural assets, walkability and accessibility, Ipswich. | ● | ● | PDF p.11 ↗ | ||
| Nicholas Street Cultural Heart Stage 3 Creation of a green and connected spine between South Street and Roderick Street to support the city's cultural assets, walkability and accessibility, Ipswich. | ● | ● | PDF p.11 ↗ | ||
| Ipswich Central Revitalisation Total | $1.7M | $5M | $6.9M | $13.6M |
Kerb and Channel
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Alfred Street Kerb and Channel Installation of kerb and channel on Alfred Street, from 53 Alfred Street to Dossie Lane, Riverview. | ● | PDF p.11 ↗ | |||
| Brisbane Road Kerb and Channel Installation of kerb and channel on Brisbane Road, between Brick Street and Cole Street, Redbank. | ● | PDF p.11 ↗ | |||
| Chermside Road Kerb and Channel Installation of new kerb and channel on Chermside Road, from McGill Street to its northern end, Basin Pocket. | ● | PDF p.11 ↗ | |||
| Ferguson Street Kerb and Channel Installation of kerb and channel on Ferguson Street, from Pine Street to its eastern end, North Ipswich. | ● | PDF p.11 ↗ | |||
| Gulland Street Kerb and Channel Installation of kerb and channel on Gulland Street, from Pine Street to its eastern end, North Ipswich. | ● | PDF p.11 ↗ | |||
| Smith Street Kerb and Channel Installation of kerb and channel on Smith Street, from Pine Mountain Road to its southern end adjacent 38 Smith Street, North Ipswich. | ● | PDF p.11 ↗ | |||
| Warwick Road Kerb and Channel Installation of kerb and channel on the northern and southern service roads of Warwick Road, including Sheehan Lane, with works on the northern service road between Perry Street and Sheehan Lane and on the southern service road from Berry Street to its southern end, Churchill. | ● | PDF p.11 ↗ | |||
| Kerb and Channel Total | — | $1.5M | $1.8M | $3.3M |
Provisional Projects
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Provisional Project Budget Budget allocation is for provisional projects that are identified and raised throughout the year. | ● | ● | ● | PDF p.11 ↗ | |
| Provisional Projects Total | $530k | $550k | $550k | $1.6M |
Sealed Gravel Roads
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Riverside Drive Upgrade Stage 1 Upgrade of Riverside Drive to a sealed rural road standard from Kholo Botanic Gardens to Sherlocks Road, Muirlea. | ● | PDF p.12 ↗ | |||
| Sealed Gravel Roads Total | — | — | $350k | $350k |
Unmaintained Gravel Roads
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bellview Road Gravel Road Upgrade Upgrade the existing unmaintained gravel road to a maintained standard on Bellview Road, Haigslea. | ● | PDF p.12 ↗ | |||
| Paten Road Gravel Road Upgrade Upgrade the existing unmaintained gravel road to a maintained standard on Paten Road, Calvert. | ● | PDF p.12 ↗ | |||
| Penny Lane Gravel Road Upgrade Upgrade the existing unmaintained gravel road to a maintained standard on Penny Lane, Calvert. | ● | PDF p.12 ↗ | |||
| Unmaintained Gravel Roads Total | — | — | $470k | $470k |
Urban Greening
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Tree Protection Zone Fencing and Bollards Installation of fencing and timber bollards adjacent to existing trees to prevent vehicular damage to the exposed tree roots. | ● | ● | ● | PDF p.12 ↗ | |
| Urban Greening Total | $20k | $20k | $20k | $60k |
Corporate Facilities — total $650k
Facility Upgrades
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Ipswich Civic Centre Forecourt Upgrade Forecourt upgrades including shade and additional weather protection at Ipswich Civic Centre, Ipswich. | ● | PDF p.12 ↗ | |||
| Springfield Central Community Centre Upgrade to District Upgrade of the Springfield Central Community Centre to district-standard facilities, Springfield Central. | ● | PDF p.12 ↗ | |||
| Facility Upgrades Total | — | $450k | $200k | $650k |
Sustainability — total $2.2M
Climate Resilience
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Climate Resilience Projects Climate Resilience Projects. | ● | ● | ● | PDF p.12 ↗ | |
| Implementation of New Net Zero Roadmap Implementation projects for the new proposed Net Zero Roadmap. | ● | ● | PDF p.12 ↗ | ||
| Climate Resilience Total | $150k | $450k | $450k | $1.1M |
Renewable Energy
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Eats Solar System Installation Installation of solar system at Eats, Nicholas Street Precinct, Ipswich. | ● | PDF p.13 ↗ | |||
| North Ipswich Reserve Solar System Installation of a 60kW+ solar PV System at North Ipswich Reserve, North Ipswich. | ● | PDF p.13 ↗ | |||
| Solar System and Electric Vehicle (EV) Charging Projects Installation of additional solar systems and EV charging stations across the city. Exact locations have not been confirmed at this point in time. | ● | PDF p.13 ↗ | |||
| Tulmur Place Solar System Installation Installation of solar system at Tulmur Place, Nicholas Street Precinct, Ipswich. | ● | PDF p.13 ↗ | |||
| Tulmur Walk Solar System Installation Installation of solar system at Tulmur Walk, Nicholas Street Precinct, Ipswich. | ● | PDF p.13 ↗ | |||
| Venue Solar System Installation Installation of solar system at Venue, Nicholas Street Precinct, Ipswich. | ● | PDF p.13 ↗ | |||
| Renewable Energy Total | $420k | $500k | $200k | $1.1M |
Resource Recovery — total $22M
Resource Recovery
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Commercial Bin Purchases Purchase of new and replacement commercial bins. | ● | ● | ● | PDF p.13 ↗ | |
| Domestic Bin Purchases Purchase of new and replacement domestic bins. | ● | ● | ● | PDF p.13 ↗ | |
| Resource Recovery Centre Works Reactive works at council's resource recovery centres. | ● | ● | ● | PDF p.13 ↗ | |
| Riverview Resource Recovery Centre Hydraulic Tipper Bins Installation of hydraulic tipper bins to improve customer safety, increase efficiency and reduce manual handling of heavy waste at the Riverview Resource Recovery Centre, Riverview. | ● | PDF p.13 ↗ | |||
| Riverview Resource Recovery Centre Internal Traffic Management Upgrade to existing road network to improve access and user experience when traveling through the Riverview Resource Recovery Centre, Riverview. | ● | ● | PDF p.13 ↗ | ||
| Riverview Resource Recovery Centre Kerb and Channelling Rehabilitation of existing kerb and channel within the Riverview Resource Recovery Centre, Riverview. | ● | PDF p.13 ↗ | |||
| Riverview Resource Recovery Centre Recycle Street Improvements to visualisations of resource recycling area at the Riverview Resource Recovery Centre, Riverview. | ● | ● | PDF p.13 ↗ | ||
| Southern Resource Recovery Centre Installation Stage 1 – Preliminary inc Geotech Installation of a new facility incorporating the Southern Resource Recovery Centre to meet the growth needs of the city. | ● | ● | ● | PDF p.13 ↗ | |
| Southern Resource Recovery Centre Installation Stage 2 – External Roadworks and Bulk Earthworks Installation of a new facility incorporating the Southern Resource Recovery Centre to meet the growth needs of the city. | ● | PDF p.13 ↗ | |||
| Western Resource Recovery Centre Installation Installation of a new Western Resource Recovery Centre to replace the existing Rosewood Resource Recovery Centre, Rosewood. | ● | PDF p.13 ↗ | |||
| Resource Recovery Total | $4.4M | $3.1M | $14.6M | $22M |
Disaster And Natural Hazard Management — total $670k
Disaster and Emergency Management
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Disaster Awareness Camera Network – Fire Detection Cameras Specialist fire detection and disaster monitoring cameras. | ● | PDF p.14 ↗ | |||
| Disaster Awareness Camera Network – Flood Cameras Cameras utilised to monitor disaster events and provide situational awareness to council and the public. To replace existing temporary cameras. | ● | ● | ● | PDF p.14 ↗ | |
| Enviromon Software Replacement This is the software system utilised by council to store flood warning infrastructure network data and share data with the Bureau of Meteorology (BOM). | ● | PDF p.14 ↗ | |||
| Government Wireless Network Radios Government Wireless Network radios. | ● | ● | PDF p.14 ↗ | ||
| Low Cost Flood Monitoring Devices Alternative low cost flood water alert devices that can be utilised to expand the council flood monitoring network in a more economic way. | ● | ● | ● | PDF p.14 ↗ | |
| Disaster and Emergency Management Total | $350k | $170k | $150k | $670k |
Asset Rehabilitation — total $179.6M
Bridge and Culvert Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Addison Road Footbridge Rehabilitation Footbridge rehabilitation works on Addison Road, Camira. | ● | PDF p.14 ↗ | |||
| Bergins Hill Road Culvert Rehabilitation Culvert rehabilitation works on Bergins Hill Road, Bundamba. | ● | ● | PDF p.14 ↗ | ||
| Bridge and Culvert Rehabilitation Projects Unidentified bridge and culvert rehabilitation projects. | ● | ● | PDF p.14 ↗ | ||
| Bridge Joint Rehabilitation Bridge joint rehabilitation works identified from routine inspections. | ● | PDF p.14 ↗ | |||
| Camira Springfield Community Centre Boardwalk Rehabilitation Boardwalk rehabilitation works at the Camira Springfield Community Centre, Camira. | ● | ● | PDF p.14 ↗ | ||
| Clem Street Footbridge Embankment Protection Embankment protection works on Clem Street footbridge, Brassall. | ● | ● | PDF p.14 ↗ | ||
| Creek Street Bridge Rehabilitation Bridge rehabilitation work on Creek Street, Bundamba. | ● | ● | PDF p.14 ↗ | ||
| Cyprus Street Retaining Wall Replacement Replacement of existing wooden retaining wall at 32 Cyprus Street, North Ipswich. | ● | ● | PDF p.14 ↗ | ||
| Fernvale Road Bridge Rehabilitation Bridge rehabilitation work on Fernvale Road, Brassall. | ● | ● | PDF p.14 ↗ | ||
| Goodna Community Centre Retaining Wall Replacement Replacement of retaining wall at Goodna Community Centre, Goodna. | ● | ● | PDF p.14 ↗ | ||
| Haig Street Footbridge Rehabilitation Footbridge rehabilitation works on Haig Street, Brassall. | ● | PDF p.14 ↗ | |||
| Hancock Bridge Barrier Replacement Replacement of the Hancock Bridge barriers, on Albion Street and Kingsmill Road, Brassall/Coalfalls. | ● | ● | PDF p.14 ↗ | ||
| Incinerator Theatre Retaining Wall Replacement Retaining wall replacement works at the Incinerator Theatre, Queens Park, Ipswich. | ● | PDF p.14 ↗ | |||
| Ipswich Bowls Club Retaining Wall Replacement Replacement of retaining wall at Ipswich Bowls Club, Ipswich. | ● | ● | PDF p.14 ↗ | ||
| Ipswich Croquet Club Retaining Wall Replacement Edge board replacement at Queens Park Croquet Club, Ipswich. | ● | ● | PDF p.14 ↗ | ||
| John Street Culvert Rehabilitation Culvert rehabilitation work on John Street, Rosewood. | ● | ● | PDF p.14 ↗ | ||
| Kholo Garden Depot Retaining Wall Replacement Replacement of retaining wall at Kholo Garden Depot, Kholo. | ● | ● | PDF p.14 ↗ | ||
| Lower James Street Bridge Rehabilitation Bridge rehabilitation work on Lower James Street, Goodna. | ● | ● | PDF p.14 ↗ | ||
| Mary Street Footbridge Replacement Footbridge rehabilitation works on Mary Street, Blackstone. | ● | PDF p.15 ↗ | |||
| McFarland Bridge Abutment Protection Bridge abutment protection works on McFarland Bridge on Mount Mort Road, Grandchester. | ● | ● | PDF p.15 ↗ | ||
| Middle Road Culvert Rehabilitation Replace the culvert located at the intersection of Middle Road and Stevens Road, Purga. | ● | PDF p.15 ↗ | |||
| Mill Street Footbridge Replacement Footbridge rehabilitation works on Mill Street, Rosewood. | ● | PDF p.15 ↗ | |||
| Nerima Gardens Pond Rehabilitation Reinstatement of pond edge and slope rehabilitation at Nerima Gardens, Ipswich. | ● | ● | PDF p.15 ↗ | ||
| Paddington Reserve Boardwalk Rehabilitation Boardwalk rehabilitation works at Paddington Reserve, Flinders View. | ● | ● | PDF p.15 ↗ | ||
| Pan Pacific Peace Gardens Footbridge Rehabilitation Footbridge rehabilitation works at Pan Pacific Peace Gardens, Redbank. | ● | ● | PDF p.15 ↗ | ||
| Popple Point Place Fence Replacement Replacement of a damaged hard wood fence at Popple Point Place, Springfield Lakes. | ● | ● | PDF p.15 ↗ | ||
| Queens Park Caretaker's Residence Retaining Wall Replacement Retaining wall replacement works at the caretaker's residence, Queens Park, Ipswich. | ● | PDF p.15 ↗ | |||
| Queens Park Retaining Wall Kerb Extension Retaining wall kerb extension works at the Ipswich Bowling Club, Queens Park, Ipswich. | ● | PDF p.15 ↗ | |||
| Riverheart Parklands Boardwalk Replacement Boardwalk replacement works at Riverheart Parklands, Ipswich. | ● | ● | PDF p.15 ↗ | ||
| Rosewood Laidley Road Culvert Replacement Culvert replacement works at Rosewood Laidley Road, Grandchester. | ● | ● | ● | PDF p.15 ↗ | |
| Sandy Creek Footbridge Replacement Footbridge replacement works on Sandy Creek, Camira. | ● | ● | PDF p.15 ↗ | ||
| Scenic Park Retaining Wall Replacement Retaining wall replacement works at Scenic Park, Brookwater. | ● | ● | PDF p.15 ↗ | ||
| Springfield Lake Park Boardwalk Rehabilitation Rehabilitation of curved deck at Springfield Lake Park, Springfield Lakes. | ● | ● | PDF p.15 ↗ | ||
| Springfield Lake Park Culvert Rehabilitation Rehabilitation of the culvert at Springfield Lake Park, Springfield Lakes. | ● | ● | ● | PDF p.15 ↗ | |
| Tallegalla Road Stormwater Culvert Rehabilitation Stage 2 Culvert rehabilitation work on Tallegalla Road, Tallegalla. | ● | PDF p.15 ↗ | |||
| Three Mile Bridge Abutment Protection Bridge abutment works on the Three Mile Bridge, Old Toowoomba Road, Leichhardt. | ● | ● | ● | PDF p.15 ↗ | |
| Bridge and Culvert Rehabilitation Total | $4.2M | $7M | $10.5M | $21.8M |
Disturbed Land Management
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Borallon Closed Landfill Remediation Rehabilitation of closed landfill site at Borallon. | ● | PDF p.15 ↗ | |||
| Brittains Road Closed Landfill Stormwater Infrastructure Remediation Remediation of failed stormwater infrastructure on Brittains Road Closed Landfill located at 63 Brittains Road, Augustine Heights and adjoining Program 30 lot 900SP300718. | ● | PDF p.15 ↗ | |||
| Disturbed Land Remediation Projects Unallocated citywide budget for planning, design and construction of disturbed land remediation projects. | ● | ● | ● | PDF p.15 ↗ | |
| Disturbed Land Site Compliance Works Reactive projects identified through routine investigations/inspections of council owned historic landfill and mine sites. | ● | ● | ● | PDF p.15 ↗ | |
| Environmental Monitoring Infrastructure Installation of telemetry monitoring systems at disused landfill sites to monitor underground gases. | ● | ● | ● | PDF p.15 ↗ | |
| Redbank Rifle Range Intersection of Duncan Street Kruger Parade Redbank Plains Landfill and Stormwater Infrastructure Works Remediation of damaged landfill and stormwater infrastructure near the intersection of Duncan Street and Kruger Parade, Redbank Plains. | ● | PDF p.15 ↗ | |||
| Whitwood Road (South) Historical Landfill Remediation Rehabilitation of the Whitwood Road (South) Historical Landfill site, New Chum, by capping and stormwater drainage works. | ● | ● | PDF p.16 ↗ | ||
| Woogaroo Closed Landfill Leachate and Gas Management Installation of leachate and gas management infrastructure at the Woogaroo Closed Landfill site, Goodna. | ● | PDF p.16 ↗ | |||
| Disturbed Land Management Total | $2.3M | $1.4M | $1.7M | $5.4M |
Drainage Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| 134–136 Lyndon Way Drain Rehabilitation Rehabilitation of the collapsed and displaced drain due to tree roots at 134–136 Lyndon Way, Karalee. | ● | PDF p.16 ↗ | |||
| Albert Street Open Drain Rehabilitation Rehabilitation of the open drain at 60B Albert Street, Rosewood. | ● | ● | ● | PDF p.16 ↗ | |
| Bergins Hill Road Drainage Channel Rehabilitation Rehabilitation of existing stormwater drainage channel on Bergins Hill Road, Bundamba. | ● | PDF p.16 ↗ | |||
| Chermside Road Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure on Chermside Road, East Ipswich. | ● | ● | PDF p.16 ↗ | ||
| Drainage Reactive Works Reactive stormwater drainage rehabilitation projects currently not identified and may be required to be completed as soon as practical. | ● | PDF p.16 ↗ | |||
| East Ipswich Catchment Drainage Rehabilitation Stage 2 Rehabilitation of existing stormwater drainage infrastructure within the East Ipswich Catchment Stage 2. | ● | PDF p.16 ↗ | |||
| East Ipswich Catchment Drainage Rehabilitation Stage 3 Rehabilitation of existing stormwater drainage infrastructure within the East Ipswich Catchment Stage 3. | ● | ● | PDF p.16 ↗ | ||
| East Ipswich Catchment Drainage Rehabilitation Stage 4 Rehabilitation of existing stormwater drainage infrastructure within the East Ipswich Catchment Stage 4. | ● | ● | ● | PDF p.16 ↗ | |
| East Ipswich Catchment Drainage Rehabilitation Stage 5 Rehabilitation of existing stormwater drainage infrastructure within the East Ipswich Catchment Stage 5. | ● | ● | PDF p.16 ↗ | ||
| East Ipswich Catchment Drainage Rehabilitation Stage 6 Rehabilitation of existing stormwater drainage infrastructure within the East Ipswich Catchment Stage 6. | ● | ● | PDF p.16 ↗ | ||
| Holly Court Detention Basin Fence Replacement Replacement of the deteriorated fence around the Holly Court detention basin, Raceview. | ● | PDF p.16 ↗ | |||
| Ipswich Cemetery Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure within the Ipswich General Cemetery, Ipswich. | ● | PDF p.16 ↗ | |||
| Lowry Lane and Colvin Street Drainage Rehabilitation Replacement of existing stormwater drainage infrastructure on Lowry Lane and Colvin Street, North Ipswich. | ● | PDF p.16 ↗ | |||
| Moffat Street Drainage Reconstruction Reconstruction of existing stormwater drainage infrastructure on Moffatt Street, Ipswich. | ● | PDF p.16 ↗ | |||
| Park Street Drainage Reconstruction Reconstruction, roof water re-alignment and verge reinstatement of the existing stormwater drainage infrastructure on Park Street, Ipswich. | ● | PDF p.16 ↗ | |||
| Park Street Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure on Park Street, Ipswich. | ● | PDF p.16 ↗ | |||
| Pryde and Hume Streets Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure adjacent to Pryde Street and Hume Street, Woodend. | ● | ● | ● | PDF p.16 ↗ | |
| Rex Street Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure on Rex Street, Eastern Heights. | ● | PDF p.16 ↗ | |||
| Rosewood Detention Basin Rehabilitation Rehabilitation of Rosewood detention basin, Rosewood. | ● | PDF p.16 ↗ | |||
| Smith Street Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure on Smith Street, North Ipswich. | ● | PDF p.16 ↗ | |||
| Springfield Lakes Lower Dam Spillway Access Rehabilitation Rehabilitation of the lower dam spillway access at Springfield Lakes. | ● | PDF p.16 ↗ | |||
| Tregair Street and Whitehill Road Drainage Reconstruction Rehabilitation of existing stormwater drainage infrastructure on Tregair Street and Whitehill Road, Newtown. | ● | PDF p.16 ↗ | |||
| Unallocated Drainage Rehabilitation Projects Unallocated drainage rehabilitation projects including design, pipe relining and replacement activities. | ● | ● | PDF p.17 ↗ | ||
| Vineyard Street Drainage Rehabilitation Rehabilitation of existing stormwater drainage infrastructure on Vineyard Street, One Mile. | ● | PDF p.17 ↗ | |||
| Woodend Catchment Drainage Rehabilitation Stage 1 Rehabilitation of existing stormwater drainage infrastructure within the Woodend Catchment Stage 1. | ● | PDF p.17 ↗ | |||
| Woodend Catchment Drainage Rehabilitation Stage 2 Rehabilitation of existing stormwater drainage infrastructure within the Woodend Catchment Stage 2. | ● | PDF p.17 ↗ | |||
| Woodend Catchment Drainage Rehabilitation Stage 3 Rehabilitation of existing stormwater drainage infrastructure within the Woodend Catchment Stage 3. | ● | PDF p.17 ↗ | |||
| Woodend Catchment Drainage Rehabilitation Stage 4 Rehabilitation of existing stormwater drainage infrastructure within the Woodend Catchment Stage 4. | ● | ● | PDF p.17 ↗ | ||
| Woodend Catchment Drainage Rehabilitation Stage 5 Rehabilitation of drainage rehabilitation and realignment works within the Woodend Catchment Stage 5. | ● | ● | PDF p.17 ↗ | ||
| Woodend Road Drainage Reconstruction Rehabilitation of existing stormwater drainage infrastructure on Woodend Road, Sadliers Crossing. | ● | PDF p.17 ↗ | |||
| Drainage Rehabilitation Total | $10.3M | $5.9M | $13.8M | $30M |
Facility Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Auto Door Renewal Program Programmed replacement and rehabilitation of council's existing automatic door assets at various council facilities across the city. | ● | PDF p.17 ↗ | |||
| Building and Facility Rehabilitation Projects Programmed replacement and rehabilitation of council's facilities across the city. | ● | PDF p.17 ↗ | |||
| Building Management System Replacement Program Replacement program for building management system equipment across council facilities to ensure efficient maintenance of temperature, humidity and indoor air quality levels. | ● | ● | PDF p.17 ↗ | ||
| Cold Room Renewal Program Programmed replacement and rehabilitation of council's existing cold room assets at its various facilities across the city. | ● | PDF p.17 ↗ | |||
| Cooneana Heritage Centre Historical Society Clubhouse Rehabilitation Renewal of the historic Motorcycle Clubhouse at the Cooneana Heritage Centre, New Chum. | ● | ● | PDF p.17 ↗ | ||
| Drinking Water Unit Replacement Program Replacement program for drinking water units within council facilities. | ● | ● | PDF p.17 ↗ | ||
| Facilities Air-Conditioning System Replacement Program Replacement of aging air-conditioning systems within council facilities. | ● | ● | ● | PDF p.17 ↗ | |
| Facilities Minor Works Program Minor facility refurbishment projects raised through the customer service request process. | ● | ● | ● | PDF p.17 ↗ | |
| Goodna SES Sewerage Connection Connection to the sewerage system at the Goodna SES facility, Redbank Plains. | ● | PDF p.17 ↗ | |||
| Incinerator Theatre and Jean Pratt Building Main Switchboard Renewal Renewal of end-of-life switchboard that services the Jean Pratt Building, Ipswich. | ● | PDF p.17 ↗ | |||
| Incinerator Theatre Chimney Refurbishment Refurbishment of the chimney at the Incinerator Theatre, Ipswich. | ● | PDF p.17 ↗ | |||
| Ipswich Art Gallery Drainage Rehabilitation Rehabilitation works required to prevent rising damp occurring at Ipswich Art Gallery, Ipswich. | ● | PDF p.17 ↗ | |||
| Ipswich Art Gallery Forecourt Refurbishment Replacement of the defective floor finishes within Ipswich Art Gallery forecourt area, Ipswich. | ● | ● | PDF p.17 ↗ | ||
| Ipswich Art Gallery Retaining Wall Renewal Renewal of timber retaining wall adjacent to Ipswich Art Gallery and Workshop, Ipswich. | ● | PDF p.17 ↗ | |||
| Ipswich Art Gallery Roof Safety System Upgrade of the roof safety system at Ipswich Art Gallery. | ● | PDF p.18 ↗ | |||
| Ipswich Art Workshop Refurbishment Minor refurbishment of fixings at Ipswich Art Workshop, Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich Civic Centre Foyer Ceiling Rehabilitation Rehabilitation of the foyer ceiling within Ipswich Civic Centre, Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich Civic Centre Gallery Amenities Rehabilitation Refurbishment of the existing gallery toilets within Ipswich Civic Centre, Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich Civic Centre Plant Deck Installation Installation of a plant deck at Ipswich Civic Centre to prevent roof leaks, Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich Civic Centre Vehicle Access Improvement Reconstruction of existing vehicular access to Ipswich Civic Centre, Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich Motorsport Precinct Main Switchboard Renewal Renewal of the main electrical switchboard at lease area J, Ipswich Motor Sport Precinct, Willowbank. | ● | PDF p.18 ↗ | |||
| Ipswich Motorsport Precinct Sewer Modifications Modification of the sewer at Ipswich Motor Sport Precinct, Willowbank. | ● | PDF p.18 ↗ | |||
| Ipswich Pound Gate Replacement Replacement of the entrance gate to Ipswich Pound, West Ipswich. | ● | PDF p.18 ↗ | |||
| Ipswich RSL Floor Levels Refurbishment Refurbishment of the floor at Ipswich RSL, Ipswich. | ● | PDF p.18 ↗ | |||
| North Ipswich Bowls Club Car Park Resurfacing Resurfacing of North Ipswich Bowls Club car park, North Ipswich. | ● | ● | PDF p.18 ↗ | ||
| Old Woollen Mills Roof Replacement Roof rectification works at Old Woollen Mills, North Ipswich. | ● | ● | ● | PDF p.18 ↗ | |
| Painting Refurbishment Program Painting refurbishments for council's existing buildings and facilities. | ● | PDF p.18 ↗ | |||
| Queens Park Bowls Club Roof Renewal Roof rectification works at Queens Park Bowls Club, Ipswich. | ● | PDF p.18 ↗ | |||
| Queens Park Café Flooring Renewal Renewal of kitchen vinyl at Queens Park Café, Ipswich. | ● | PDF p.18 ↗ | |||
| Riverview Depot Lower Car Park Rehabilitation Rehabilitation of the lower car park pavement at Riverview Depot, Riverview. | ● | ● | PDF p.18 ↗ | ||
| Robelle Domain Display Unit Replacement Replacement of the LED multifunction display unit at The Circle, Robelle Domain, Springfield Central. | ● | PDF p.18 ↗ | |||
| Roof Refurbishment Program Programmed minor refurbishments of council's existing roof assets at its various facilities across the city. | ● | PDF p.18 ↗ | |||
| Switchboard Renewal Program Programmed renewal of council's existing electrical switchboard assets at its various facilities across the city. | ● | PDF p.18 ↗ | |||
| Tallegalla House Refurbishment Various refurbishment works of Tallegalla House, Tallegalla. | ● | PDF p.18 ↗ | |||
| Water Heating Equipment Renewal Program Programmed renewal of council's existing hot water units and thermostatic mixing valves assets at its various facilities across the city. | ● | PDF p.18 ↗ | |||
| Facility Rehabilitation Total | $3.1M | $3.2M | $2.3M | $8.7M |
Gravel Road Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Gravel Resheeting Program Reconstruction of existing gravel roads across the city. Locations are based on routine inspections and service requests. | ● | ● | ● | PDF p.18 ↗ | |
| Gravel Road Rehabilitation Total | $2M | $2.6M | $2.7M | $7.3M |
Kerb and Channel Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Argyle Street Kerb and Channel Rehabilitation Road reconstruction on Argyle Street, between Henty Drive to Price Close and 40 to 50 Argyle Street, Redbank Plains. | ● | ● | PDF p.19 ↗ | ||
| Edgar Street Kerb and Channel Rehabilitation Reconstruct a section of kerb and channel on Edgar Street, from Whitehill Road to Minnis Street, Eastern Heights. | ● | ● | PDF p.19 ↗ | ||
| Frederick Street Kerb and Channel Rehabilitation Reconstruct a section of kerb and channel on Frederick Street, from Glebe Road to George Street, Newtown. | ● | ● | PDF p.19 ↗ | ||
| Gladstone Road Kerb and Channel Rehabilitation Reconstruction of kerb and channel from 1 to 21 Gladstone Road, Sadliers Crossing. | ● | ● | ● | PDF p.19 ↗ | |
| Holt Street Kerb and Channel Rehabilitation Road reconstruction on Holt Street, from Glenelg Drive to end, Brassall. | ● | ● | PDF p.19 ↗ | ||
| Minor Kerb and Channel Rehabilitation Unallocated Program Unallocated budget for reactive kerb and channel rehabilitation projects. | ● | PDF p.19 ↗ | |||
| Queen Street Kerb and Channel Rehabilitation Reconstruct a section of kerb and channel on Queen Street, from Blackstone Road to George Street, Newtown. | ● | ● | PDF p.19 ↗ | ||
| Royal George Lane Kerb and Channel Rehabilitation Road reconstruction works on Royal George Lane, from John Street to Albert Street, Rosewood. | ● | ● | PDF p.19 ↗ | ||
| Russell Drive Kerb and Channel Rehabilitation Road reconstruction works on Russell Drive, from Llewellyn Street to 65 Russell Drive, Redbank Plains. | ● | ● | ● | PDF p.19 ↗ | |
| Trevlac Street Kerb and Channel Rehabilitation Road reconstruction on Trevlac Street, Rosewood. | ● | ● | PDF p.19 ↗ | ||
| View Street Kerb and Channel Rehabilitation Road reconstruction on View Street, from Panton Street to 12 View Street, Woodend. | ● | ● | ● | PDF p.19 ↗ | |
| West Street Kerb and Channel Rehabilitation Reconstruct a section of kerb and channel on West Street, from Darling Street East to Mary Street, Woodend. | ● | ● | PDF p.19 ↗ | ||
| Kerb and Channel Rehabilitation Total | $835k | $1.2M | $2.9M | $5M |
Parks Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Battye Park Playground Replacement Replacement of existing playground equipment at Battye Park, Brassall. | ● | ● | PDF p.19 ↗ | ||
| Castle Hill Blackstone Reserve Car Park Refurbishment Refurbishment of the existing car park at Castle Hill Blackstone Reserve, Blackstone. | ● | PDF p.19 ↗ | |||
| Grande Park Playground Replace the mountain slide and relocate the maintenance access gate at Grande Park, Springfield Lakes. | ● | PDF p.19 ↗ | |||
| Griffiths Park Playground Replacement Replacement of existing playground equipment at Griffiths Park, Bellbird Park. | ● | ● | PDF p.19 ↗ | ||
| Haig Street Conservation Reserve Bollards Replacement of the existing timber bollards with recycled plastic bollards at the Haig Street Conservation Reserve, Brassall. | ● | PDF p.19 ↗ | |||
| Hancock Park Playground Replacement Replacement of play equipment at Hancock Park, Eastern Heights. | ● | ● | PDF p.19 ↗ | ||
| Hayden Park Play Equipment Renewal Renewal of general play equipment at Hayden Park, Riverview. | ● | ● | PDF p.19 ↗ | ||
| Johnston Park Play Equipment Renewal Replacement of play equipment unit and shade sail pole removal at Johnston Park, Rosewood. | ● | PDF p.19 ↗ | |||
| Lakes Entrance Park Play Equipment Renewal Renewal of general play equipment and fencing at Lakes Entrance Park, Springfield Lakes. | ● | PDF p.19 ↗ | |||
| Leichhardt Park Swing Replacement Replacement of the swing set at Leichhardt Park, One Mile. | ● | PDF p.19 ↗ | |||
| Len Shearer Park Play Equipment Rehabilitation Replacement of the existing play equipment at Len Shearer Park, Bellbird Park. | ● | PDF p.19 ↗ | |||
| Limestone Park Boundary Bollard Replacement Replacement of existing timber bollards surrounding Limestone Park, Ipswich. | ● | PDF p.20 ↗ | |||
| Limestone Park Fitness Equipment Replacement Relocation and replacement of the existing fitness equipment within Limestone Park, Ipswich. | ● | ● | PDF p.20 ↗ | ||
| Lobley Park Play Equipment Rehabilitation Replacement of the existing play equipment and lighting at Lobley Park, Churchill. | ● | PDF p.20 ↗ | |||
| Marsh Park Shade Structure Renewal Replacement of the shade sail structure at Marsh Park, Raceview. | ● | ● | PDF p.20 ↗ | ||
| Neumann Family Park Play Equipment Rehabilitation Renewal of the existing play equipment and softfall edging at Neumann Family Park, Leichhardt. | ● | PDF p.20 ↗ | |||
| Norm Craswell Park Play Equipment Renewal Playground renewal works at Norm Craswell Park, Redbank Plains. | ● | PDF p.20 ↗ | |||
| Organic Softfall Replacement Rehabilitation of existing playground organic/mulch softfall identified through the internal and external service request process. | ● | ● | ● | PDF p.20 ↗ | |
| Orion Lagoon Lighting Replacement Replacement of lighting at the Orion Lagoon, Springfield Central. | ● | PDF p.20 ↗ | |||
| Paddington Reserve Playground Replacement Replacement of the existing playground within Paddington Reserve, Flinders View. | ● | PDF p.20 ↗ | |||
| Parks Refurbishment Reactive Works Reactive works within parks and identified through the internal and external service request process. | ● | ● | ● | PDF p.20 ↗ | |
| Playground Rehabilitation Program Reactive playground refurbishment works within parks and identified through the internal and external service request process. | ● | ● | ● | PDF p.20 ↗ | |
| Regatta Walk Teenage Playground Rehabilitation Replacement of the climbing unit at the teenage playground section of Regatta Walk, Springfield Lakes. | ● | ● | PDF p.20 ↗ | ||
| Robelle Domain Perimeter Lighting Additional security lighting for the council compound at Robelle Domain, Springfield Central. | ● | PDF p.20 ↗ | |||
| Rotary Bicentennial Park Softfall Rehabilitation Replacement of organic softfall with synthetic softfall at Rotary Bicentennial Park, Redbank Plains. | ● | PDF p.20 ↗ | |||
| Rourkes Park Play Area Rehabilitation Replacement of existing playground at Rourkes Park, Flinders View. | ● | ● | PDF p.20 ↗ | ||
| Rubber Softfall Replacement Rehabilitation of existing playground rubber softfall. These locations are determined from routine playground inspections and by the service request process. | ● | ● | ● | PDF p.20 ↗ | |
| Shade Sail Replacement Replacement of existing shade sails at various locations across the city. | ● | ● | ● | PDF p.20 ↗ | |
| Shapcott Park Canoe Ramp Renewal Renewal of the canoe ramp at Shapcott Park, Coalfalls. | ● | ● | PDF p.20 ↗ | ||
| Springfield Central Sports Complex Shade Structure Renewal Shade structure renewal at Springfield Central Sports Complex, Springfield Central. | ● | ● | PDF p.20 ↗ | ||
| Streeton Park Bollard Rehabilitation Rehabilitation of the timber bollards at Streeton Park, Redbank Plains. | ● | PDF p.20 ↗ | |||
| Sutton Park Fitness Equipment Renewal Renewal of the existing fitness equipment at Sutton Park, Brassall. | ● | PDF p.20 ↗ | |||
| Sutton Park Playground Replacement Replacement of the existing playground at Sutton Park, Brassall. | ● | PDF p.20 ↗ | |||
| The Cricket Pitch Play Area Rehabilitation Replacement of the existing playground at The Cricket Pitch, Pine Mountain. | ● | PDF p.20 ↗ | |||
| Thomas and Rose Woods Park Shade Structure Renewal Shade structure renewal at Thomas and Rose Woods Park, Redbank Plains. | ● | PDF p.20 ↗ | |||
| Parks Rehabilitation Total | $2.9M | $2.6M | $2.8M | $8.4M |
Path Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Argyle Street Footpath Rehabilitation Replacement of a section of footpath at Argyle Street, Redbank Plains. | ● | ● | PDF p.20 ↗ | ||
| Atlantic Drive Sporting Complex Footpath Rehabilitation Replacement of a section of footpath affected by tree roots along the Atlantic Drive Sporting Complex, Springfield Lakes. | ● | ● | ● | PDF p.20 ↗ | |
| Byrne Street Footpath Rehabilitation Replacement and upgrade of the footpath on Byrne Street, Bundamba. | ● | PDF p.21 ↗ | |||
| Charlotte Street Footpath Rehabilitation Treatment of a section of footpath and fence installation at Charlotte Street, Blackstone. | ● | ● | PDF p.21 ↗ | ||
| Hume Street Footpath Rehabilitation Replacement of a section of footpath and construction of retaining wall to ensure slope stability at Hume Street, Woodend. | ● | ● | ● | PDF p.21 ↗ | |
| Lorikeet Street Reserve Footpath Rehabilitation Replacement of a section of footpath at Lorikeet Street Reserve, Bundamba. | ● | ● | PDF p.21 ↗ | ||
| Path Rehabilitation Projects Rehabilitation of existing pedestrian pathways. These locations are determined from routine inspections and by the service request process. | ● | ● | ● | PDF p.21 ↗ | |
| Sharpless Road Footpath Rehabilitation Replacement of a section of footpath on Sharpless Road, Springfield. | ● | ● | PDF p.21 ↗ | ||
| Tallon Street Footpath Rehabilitation Replacement of a section of footpath on Tallon Street, Sadliers Crossing. | ● | PDF p.21 ↗ | |||
| Warwick Road Footpath Rehabilitation Stormwater mitigation works by elevating the footpath and kerb and channel ramp at 28 Warwick Road, Ipswich. | ● | PDF p.21 ↗ | |||
| Wellness Way Footpath Rehabilitation Replacement of a section of footpath affected by tree roots along St Peters Lutheran College on Wellness Way, Springfield Central. | ● | ● | PDF p.21 ↗ | ||
| Whitehill Road Footpath Rehabilitation Replacement of a section of footpath on Whitehill Road, Eastern Heights. | ● | ● | PDF p.21 ↗ | ||
| Path Rehabilitation Total | $1.2M | $1M | $1.2M | $3.5M |
Sealed Road Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Albert Street Road Rehabilitation Road pavement reconstruction works on Albert Street, Rosewood. | ● | ● | ● | PDF p.21 ↗ | |
| Augusta Parkway Road Rehabilitation Road pavement reconstruction works on a section of Augusta Parkway, Augustine Heights/Brookwater. | ● | PDF p.21 ↗ | |||
| Boundary Street Rehabilitation Road pavement reconstruction works on Boundary Street, Moores Pocket. | ● | ● | PDF p.21 ↗ | ||
| Brisbane Terrace Road Rehabilitation Stage 1 Road pavement reconstruction works on Brisbane Terrace, from Lower James Street to the east of George Street, Goodna. | ● | PDF p.21 ↗ | |||
| Brisbane Terrace Road Rehabilitation Stage 2 Road pavement reconstruction works on Brisbane Terrace, from Lower Cross Street to 235 Brisbane Terrace, Goodna. | ● | PDF p.21 ↗ | |||
| Burgoyne Street Road Rehabilitation Road pavement reconstruction works on Burgoyne Street, from 19/21 to 37 Burgoyne Street, Bundamba. | ● | PDF p.21 ↗ | |||
| Cedar Road Rehabilitation Stage 1 Road pavement reconstruction works on Cedar Road, from 81 to 101 Cedar Road, Redbank Plains. | ● | ● | PDF p.21 ↗ | ||
| Cedar Road Rehabilitation Stage 2 Road pavement reconstruction works on Cedar Road, Redbank Plains. | ● | ● | PDF p.21 ↗ | ||
| Church Street Road Rehabilitation Road pavement reconstruction works on Church Street, Goodna. | ● | PDF p.21 ↗ | |||
| Citywide Sealed Road Resurfacing Road resurfacing works at various locations across the city. | ● | ● | ● | PDF p.21 ↗ | |
| Citywide Sealed Road Resurfacing – Forward Design Road resurfacing scoping and design at various locations across the city. | ● | ● | ● | PDF p.21 ↗ | |
| Claus Road Rehabilitation Road pavement reconstruction works on Claus Road, Haigslea. | ● | PDF p.21 ↗ | |||
| Cobalt Street Road Rehabilitation Road pavement reconstruction works on Cobalt Street, from 67 Boundary Steet to Emery Street, Carole Park. | ● | PDF p.21 ↗ | |||
| Collingwood Drive Road Rehabilitation Road pavement reconstruction works on Collingwood Drive, Collingwood Park. | ● | ● | PDF p.21 ↗ | ||
| Creek Street Road Rehabilitation Road pavement reconstruction works on Creek Street, between Mining Street to 62 Creek Street, Granville entrance, Bundamba. | ● | ● | ● | PDF p.22 ↗ | |
| Dellvene Crescent Road Rehabilitation Road pavement reconstruction works on Dellvene Crescent, Rosewood. | ● | ● | PDF p.22 ↗ | ||
| Dudleigh Street Road Rehabilitation Road pavement reconstruction works on Dudleigh Street, Booval. | ● | PDF p.22 ↗ | |||
| Griffith Road Rehabilitation Road pavement reconstruction works on Griffith Road, from 2A to 2B Griffith Road, Ipswich. | ● | PDF p.22 ↗ | |||
| Johnston Street Road Rehabilitation Road pavement reconstruction works on a section of Johnston Street, Bellbird Park. | ● | PDF p.22 ↗ | |||
| Junction Road Rehabilitation Road pavement reconstruction works on Junction Road, Karalee. | ● | ● | ● | PDF p.22 ↗ | |
| Lansdowne Way Road Rehabilitation Road pavement reconstruction works on Lansdowne Way, Chuwar. | ● | PDF p.22 ↗ | |||
| Lobb Street Road Rehabilitation Road pavement reconstruction works on Lobb Street, Churchill. | ● | ● | PDF p.22 ↗ | ||
| Marvin Street Road Rehabilitation Road pavement reconstruction works on Marvin Street, Eastern Heights. | ● | PDF p.22 ↗ | |||
| Mary Street Road Rehabilitation Road pavement reconstruction works on Mary Street, Blackstone. | ● | ● | ● | PDF p.22 ↗ | |
| Mica Street Road Rehabilitation Road pavement reconstruction works on Mica Street, Carole Park. | ● | PDF p.22 ↗ | |||
| Old Logan Road Rehabilitation Road pavement reconstruction works on Old Logan Road, Camira. | ● | PDF p.22 ↗ | |||
| Purga School Road Widening Purga School Road rehabilitation and widening to align with the new bridge, Purga. | ● | PDF p.22 ↗ | |||
| Redbank Plains Road Rehabilitation Road pavement reconstruction works on Redbank Plains Road, Redbank Plains. | ● | ● | ● | PDF p.22 ↗ | |
| Reif Street Road Rehabilitation Road pavement reconstruction works on Reif Street, from Ripley Road to Whitehill Road roundabout, Flinders View. | ● | ● | PDF p.22 ↗ | ||
| River Road Rehabilitation Road pavement reconstruction works on a section of River Road, Redbank. | ● | ● | ● | PDF p.22 ↗ | |
| Springfield Lakes Boulevard Road Rehabilitation Road pavement reconstruction works on Springfield Lakes Boulevard, Springfield Lakes. | ● | ● | PDF p.22 ↗ | ||
| Taloma Avenue Road Rehabilitation Road pavement reconstruction works on Taloma Avenue, Chuwar. | ● | ● | PDF p.22 ↗ | ||
| Vivian Street Road Rehabilitation Road pavement reconstruction works on a section of Vivian Street, between Minnis Street and Frederick Street, Eastern Heights. | ● | ● | PDF p.22 ↗ | ||
| Whitehill Road Rehabilitation Road pavement reconstruction works on Whitehill Road, from Cascade Street to the culvert, south of Pendragon Street, Raceview. | ● | ● | ● | PDF p.22 ↗ | |
| Willowtree Drive Road Rehabilitation Road pavement reconstruction works on a section of Willowtree Drive, from Dianthus Place to 30 Willowtree Drive, Flinders View. | ● | ● | PDF p.22 ↗ | ||
| Woodend Road Rehabilitation Road pavement reconstruction works on Woodend Road, Woodend. | ● | ● | PDF p.22 ↗ | ||
| Sealed Road Rehabilitation Total | $17.6M | $18.6M | $30.7M | $66.9M |
Sports Facility Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Andre Ripoll Remote Control Track Renewal Renewal of remote control track due to age and accumulated defects at Andre Ripoll Park, Carole Park. | ● | ● | PDF p.22 ↗ | ||
| Anzac Park Oval A Lighting Replacement Replacement of existing lighting at Oval A, Anzac Park, Rosewood. | ● | PDF p.22 ↗ | |||
| Aquatic Facility Electrical Rehabilitation Program Citywide rehabilitation program for electrical items supporting at council’s aquatic facilities. | ● | ● | PDF p.22 ↗ | ||
| Atlantic Drive Sporting Complex Tennis Court Lighting Replacement Replacement of the tennis court lights and poles within the Atlantic Drive Sporting Complex, Springfield Lakes. | ● | PDF p.22 ↗ | |||
| Bob Gamble Park Zero- Depth Shade Sail Renewal Renewal of the shade sails over the zero depth water park and adjacent areas at Bob Gamble Park, Ipswich. | ● | ● | ● | PDF p.23 ↗ | |
| Bundamba Swim and Gym Centre Artificial Surface Renewal Remediation of the wet area artificial surface at the Bundamba Swim and Gym Centre, Bundamba. | ● | ● | PDF p.23 ↗ | ||
| Bundamba Swim and Gym Centre Shade Sail Renewal Renewal and redesign of the shade sail located over the zero depth pool at Bundamba Swim and Gym Centre, Bundamba. | ● | PDF p.23 ↗ | |||
| Caledonian Park Sports Field Lighting Rehabilitation Renewal of sports field lighting at Caledonian Park, Thagoona. | ● | PDF p.23 ↗ | |||
| Ebbw Vale Memorial Park Sports Field Lighting Renewal Renewal of the lighting at the Ebbw Vale Memorial Park sports field, Ebbw Vale. | ● | PDF p.23 ↗ | |||
| Electrical Pit Rehabilitation Works Citywide rehabilitation program for electrical pits at council’s sporting facilities. | ● | ● | ● | PDF p.23 ↗ | |
| Evan Marginson Park Retaining Wall Rehabilitation Rehabilitation of the existing spectator retaining wall between the netball courts and gym building at Evan Marginson Park, Goodna. | ● | PDF p.23 ↗ | |||
| Goodna Aquatic Centre Fence Renewal Renewal of the perimeter pool safety fencing at the Goodna Aquatic Centre, Goodna. | ● | ● | PDF p.23 ↗ | ||
| Goodna Aquatic Centre Pump Room Renewal Extensive renewal of the pumproom structure housing dosing and filtration equipment at the Goodna Aquatic Centre, Goodna. | ● | ● | PDF p.23 ↗ | ||
| Goodna Rugby League Club Refurbishment Works Refurbishment works at the Goodna Rugby League Club, Goodna. | ● | ● | PDF p.23 ↗ | ||
| Grande Park Tennis Court Renewal Renewal of the Grande Park tennis court including fencing, lighting and drainage rehabilitation, Springfield Lakes. | ● | ● | PDF p.23 ↗ | ||
| Ipswich Motorsport Precinct Lease A Fencing Replacement Replace fencing at the West Moreton Auto Club, Willowbank. | ● | PDF p.23 ↗ | |||
| Leichhardt Park Aquatic Centre Shed Renewal Renewal of end-of-life shed at the Leichhardt Park Aquatic Centre, Leichhardt. | ● | ● | PDF p.23 ↗ | ||
| Limestone Park Bill Paterson Oval Irrigation Rehabilitation Irrigation refurbishment on Bill Paterson Oval, Limestone Park, Ipswich. | ● | PDF p.23 ↗ | |||
| Limestone Park Cricket Net Lighting Renewal Renewal of existing cricket net lighting at Limestone Park, Ipswich. | ● | ● | PDF p.23 ↗ | ||
| Limestone Park Netball Facility Court Resurfacing Resurfacing of existing netball courts at Limestone Park, Ipswich. | ● | PDF p.23 ↗ | |||
| Pool Blanket Replacement Program Citywide replacement program for pool blankets at council's aquatic centres. | ● | ● | ● | PDF p.23 ↗ | |
| Redbank Collingwood Park Sports Centre Outdoor Court Renewal Outdoor court renewal at the Redbank Collingwood Park Sports Centre, Redbank. | ● | ● | PDF p.23 ↗ | ||
| Redbank Plains Recreation Reserve Field Dugouts Renewal Renewal of the dugouts at Redbank Plains Recreation Reserve, Redbank Plains. | ● | ● | PDF p.23 ↗ | ||
| Redbank Plains Recreation Reserve Oval A Lighting Replacement Replacement of existing lighting at Oval A, Redbank Plains Recreation Reserve, Redbank Plains. | ● | PDF p.23 ↗ | |||
| Redbank Plains Recreation Reserve Oval F and G Lighting Replacement Replacement of existing lighting at Oval F and G, Redbank Plains Recreation Reserve, Redbank Plains. | ● | PDF p.23 ↗ | |||
| Rosewood Aquatic Centre Changeroom Flooring Renewal Renewal of the changeroom flooring at Rosewood Aquatic Centre, Rosewood. | ● | PDF p.23 ↗ | |||
| Rosewood Aquatic Centre Facility Renewal Renewal of the Rosewood Aquatic Centre, Rosewood. | ● | ● | PDF p.23 ↗ | ||
| Rosewood Aquatic Centre Facility Upgrades Upgrade of the Rosewood Aquatic Centre as an outcome of the Aquatic Facilities Action Plan, Rosewood. | ● | PDF p.23 ↗ | |||
| Sports Facility Irrigation Metering and Control Remediation Remediation of known irrigation water usage controls to prevent water wastage and unnecessary repairs and site monitoring. | ● | PDF p.23 ↗ | |||
| Sports Facility Irrigation Rehabilitation Program Citywide program for rehabilitation and renewal of council's sports field irrigation systems. | ● | ● | PDF p.24 ↗ | ||
| Sports Facility Rehabilitation Projects Reactive sports facility rehabilitation projects based on customer requests and condition assessments. | ● | ● | ● | PDF p.24 ↗ | |
| Sports Field Lighting Reactive Works Reactive replacement of non-conforming sports field lighting across the city. | ● | ● | ● | PDF p.24 ↗ | |
| Springfield Central Sports Complex Facility Lighting Renewal Renewal of facility lighting at Springfield Central Sports Complex, Springfield Central. | ● | ● | PDF p.24 ↗ | ||
| Springfield Central Sports Complex Netball Court Lighting Renewal Renewal of lighting at the netball court, Springfield Central Sports Complex, Springfield Central. | ● | PDF p.24 ↗ | |||
| Tivoli Sporting Complex Dugouts and Structures Renewal Complete renewal of various steel exterior structures at the Tivoli Sporting Complex, Tivoli. | ● | ● | PDF p.24 ↗ | ||
| Woodend Park Oval A Lighting Replacement Replacement of existing lighting at Oval A, Woodend Park, Woodend. | ● | PDF p.24 ↗ | |||
| Sports Facility Rehabilitation Total | $5.9M | $2.7M | $3.8M | $12.3M |
Street Furniture Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Guard Rail Roadside Furniture Reinstatement Reactive and unplanned guardrail replacement across the city. | ● | ● | ● | PDF p.24 ↗ | |
| Old Logan and Addison Road Traffic Signal Refurbishment Replacement of the traffic signal controller system and overhead lanterns at Old Logan Road, Addison Road and Cairns Road intersection, Camira. | ● | PDF p.24 ↗ | |||
| Redbank Plains Road Traffic Signal Replacement Replacement of the traffic signal controller system and overhead lanterns at Redbank Plains Road, and at the signalised pedestrian crossing between Kruger Parade and Eagle Street, Bellbird Park. | ● | PDF p.24 ↗ | |||
| Road Pavement Marking Reinstatement Programmed pavement marking replacement across the city. | ● | ● | ● | PDF p.24 ↗ | |
| Traffic Facilities Reinstatement Unplanned and programmed street furniture replacement across the city. | ● | ● | ● | PDF p.24 ↗ | |
| Traffic Signal Refurbishment Rehabilitation of existing traffic signals. | ● | ● | PDF p.24 ↗ | ||
| Street Furniture Rehabilitation Total | $2M | $2.1M | $2.5M | $6.6M |
Water Quality Rehabilitation
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Bremervale Park Bioretention Basins Rehabilitation Rehabilitation of three bonded bioretention basins at Bremervale Park, Raceview. | ● | ● | ● | PDF p.24 ↗ | |
| Deebing Heights Bioretention Basins Rehabilitation Rehabilitation of three bonded bioretention basins at Deebing Heights. | ● | ● | ● | PDF p.24 ↗ | |
| Robelle Domain Silt Mitigation Detailed design of the Robelle Domain Lagoon to aid the ongoing management of sedimentation in the Lagoon, Springfield Central. | ● | PDF p.24 ↗ | |||
| Santa Monica Drive Wetlands Rehabilitation Wetlands rectification works at Santa Monica Drive, Augustine Heights. | ● | ● | ● | PDF p.24 ↗ | |
| Waterside Drive Bioretention Basin Rehabilitation Rectification of the bioretention basin spillway at Waterside Drive, Springfield Lakes. | ● | ● | ● | PDF p.24 ↗ | |
| Water Quality Rehabilitation Total | $1M | $1.1M | $1.7M | $3.8M |
Fleet — total $41.8M
Fleet
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Major Plant Growth Purchase new major plant to meet the growth demand of the city. | ● | ● | PDF p.25 ↗ | ||
| Major Plant Replacement Replacement of major plant assets. | ● | ● | ● | PDF p.25 ↗ | |
| Minor Plant Replacement Replacement of minor plant assets. | ● | ● | ● | PDF p.25 ↗ | |
| Motor Vehicle Replacement Replacement of motor vehicle assets. | ● | ● | ● | PDF p.25 ↗ | |
| Truck Replacement Replacement of truck assets. | ● | ● | ● | PDF p.25 ↗ | |
| Waste Truck Replacement Replacement of waste truck assets. | ● | ● | ● | PDF p.25 ↗ | |
| Waste Trucks Domestic Growth Purchase new waste trucks for collection of domestic bins to meet the growth demand of the city. | ● | ● | PDF p.25 ↗ | ||
| Fleet Total | $6.4M | $13.2M | $22.2M | $41.8M |
Other — total $84.2M
Emergent Works
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Emergent Works Contingency budget for emergent works. | ● | ● | ● | PDF p.25 ↗ | |
| Emergent Works Total | $2M | $2M | $2M | $6M |
Specialist Equipment
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Office Furniture Purchase of new and replacement of existing council furniture. | ● | ● | ● | PDF p.25 ↗ | |
| Specialist Equipment Purchase of new and replacement of existing specialised equipment. | ● | ● | ● | PDF p.25 ↗ | |
| Survey Equipment Purchase of new and replacement of existing survey equipment. | ● | ● | ● | PDF p.25 ↗ | |
| Specialist Equipment Total | $299k | $286k | $291k | $876k |
Other Capital Projects
| Project | 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total | Source |
|---|---|---|---|---|---|
| Corporate Projects Including Nicholas Street Precinct, and upgrades to cemeteries, pound, community facilities, art gallery and libraries. | ● | ● | ● | PDF p.25 ↗ | |
| Disaster Recovery Including Flood and Weather Event Recovery. | ● | PDF p.25 ↗ | |||
| Information Communication and Technology Infrastructure replacement and upgrades. | ● | ● | ● | PDF p.25 ↗ | |
| North Ipswich Sport and Entertainment Precinct North Ipswich Sport and Entertainment Precinct Stage 1: Western Grandstand. | ● | ● | PDF p.25 ↗ | ||
| Other Capital Projects Total | $35.4M | $28.6M | $13.3M | $77.3M |
Grand total
| 2026–2027 | 2027–2028 | 2028–2029 | 3 Year Total |
|---|---|---|---|
| $209.8M | $234.4M | $227.6M | $671.7M |
Source: Ipswich City Council Capital Works Program 2026–2029 (CC BY 4.0).