Home › Projects › Burgoyne Street Road Rehabilitation
Burgoyne Street Road Rehabilitation
Description
Council is undertaking road pavement reconstruction works between on Burgoyne Street, Bundamba.
Status
Construction is expected to commence in mid-September 2026 and be completed by late October 2026. Please see the Notification of Works for more information.
What to expect
You may experience changed traffic conditions, delays in access in and out of properties, increase of noise from machinery, partial lane closures,light delays and traffic control on site. Some night works as necessary.
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Sealed Road Rehabilitation · as “Burgoyne Street Road Rehabilitation”) Council source ↗
Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Sealed Road Rehabilitation · as “Burgoyne Street Road Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $5k | $400k | — | $405k |
Capital Works Program 2024–2027 (2024–2025 budget · Sealed Road Rehabilitation · as “Burgoyne Street Road Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $45k | — | $342k | $387k |
Capital Works Program 2023–2026 (2023–2024 budget · Sealed Road Rehabilitation · as “Burgoyne Street Road Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | $30k | $305k | $335k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 revised | $30,000 | $45,000 | · |
| 2025–2026 revised | $305,000 | – | $5,000 |
| 2026–2027 revised | · | $342,000 | $400,000 |
| 2027–2028 | · | · | – |
Council published different figures for 2024–2025, 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027
Capital Works Program (PDF) - 2025–2026Listed at $405k over three years
Capital Works Program (PDF) - 2024–2025Listed at $387k over three years
Capital Works Program (PDF) - 2023–2024Listed at $335k over three years
Capital Works Program (PDF)
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).