What's Being Planned · Suburb: Goodna · Ref: INF05533 · Last updated: 2026-10-01

Description

Ipswich City Council is planning to undertake bridge rehabilitation works on Lower James Street Bridge, Goodna

Status

This project is currently in the design stage and construction is anticipated to commence in the 2027 - 2028 financial year, subject to Council's budget process.

What to expect

Currently in design phase

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Bridge and Culvert Rehabilitation · as “Lower James Street Bridge Rehabilitation”) Council source ↗

Funded in 2026–2027 and 2027–2028 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Bridge and Culvert Rehabilitation · as “Lower James Street Bridge Rehabilitation”) Council source ↗

2025–20262026–20272027–20283 Year Total
—$10k$130k$140k

Capital Works Program 2024–2027 (2024–2025 budget · Bridge and Culvert Rehabilitation · as “Lower James Street Bridge Rehabilitation”) Council source ↗

2024–20252025–20262026–20273 Year Total
—$5k$130k$135k

Funding, as published in each program

Financial year2024–2025 program2025–2026 program
2024–2025–·
2025–2026$5,000–
2026–2027 revised$130,000$10,000
2027–2028·$130,000

Council published different figures for 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.