Evan Marginson Park Retaining Wall Rehabilitation
Description
Council is planning to rehabilitate the existing spectator retaining wall between the netball courts and gym building at Evan Marginson Park, Goodna.
Status
This project design is complete. Construction timing will be dependent on funding in future Council budgets.
What to expect
Sections of the park will be unavailable during construction
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Sports Facility Rehabilitation · as “Evan Marginson Park Retaining Wall Rehabilitation”) Council source ↗
Funded in 2027–2028 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Sports Facility Rehabilitation · as “Evan Marginson Park Retaining Wall Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $70k | — | $350k | $420k |
Capital Works Program 2024–2027 (2024–2025 budget · Sports Facility Rehabilitation · as “Evan Marginson Park Retaining Wall Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $30k | $70k | $350k | $450k |
Capital Works Program 2023–2026 (2023–2024 budget · Sports Facility Rehabilitation · as “Evan Marginson Park Retaining Wall Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | — | $100k | $100k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 | – | $30,000 | · |
| 2025–2026 revised | $100,000 | $70,000 | $70,000 |
| 2026–2027 | · | $350,000 | – |
| 2027–2028 | · | · | $350,000 |
Council published different figures for 2025–2026 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2027–2028
Capital Works Program (PDF) - 2025–2026Listed at $420k over three years
Capital Works Program (PDF) - 2024–2025Listed at $450k over three years
Capital Works Program (PDF) - 2023–2024Listed at $100k over three years
Capital Works Program (PDF)
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).