HomeProjects › Trevlac Street Kerb and Channel Rehabilitation

Trevlac Street Kerb and Channel Rehabilitation

What's Being Planned · Suburb: Rosewood · Ref: INF05304 · Last updated: 2026-08-19

Description

Council is planning road pavement reconstruction works on Trevlac Street, Rosewood.

Status

This project is currently in concept design phase and is expected to move into the detailed design phase in the 2026-2027 financial year. Construction timing will be dependent on funding in future Council budgets.

What to expect

You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Kerb and Channel Rehabilitation · as “Trevlac Street Kerb and Channel Rehabilitation”) Council source ↗

Funded in 2026–2027 and 2028–2029 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Kerb and Channel Rehabilitation · as “Trevlac Street Kerb and Channel Rehabilitation”) Council source ↗

2025–20262026–20272027–20283 Year Total
$75k$50k$125k

Capital Works Program 2024–2027 (2024–2025 budget · Kerb and Channel Rehabilitation · as “Trevlac Street Kerb and Channel Rehabilitation”) Council source ↗

2024–20252025–20262026–20273 Year Total
$50k$55k$105k

Capital Works Program 2023–2026 (2023–2024 budget · Kerb and Channel Rehabilitation · as “Trevlac Street Kerb and Channel Rehabilitation”) Council source ↗

2023–20242024–20252025–20263 Year Total
$40k$40k

Funding, as published in each program

Financial year2023–2024 program2024–2025 program2025–2026 program
2023–2024··
2024–2025·
2025–2026 revised$40,000$50,000$75,000
2026–2027 revised·$55,000$50,000
2027–2028··

Council published different figures for 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).