Home › Projects › Bergins Hill Road Drainage Channel Rehabilitation
Bergins Hill Road Drainage Channel Rehabilitation
Description
Council is planning rehabilitation of the existing stormwater drainage channel on Bergins Hill Road Bundamba.
Status
Construction timing will be dependent on funding in future Council budgets.
What to expect
Currently in design phase
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗
Funded in 2028–2029 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| — | — | $1M | $1M |
Capital Works Program 2024–2027 (2024–2025 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $80k | $70k | $300k | $450k |
Capital Works Program 2023–2026 (2023–2024 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| $15k | $80k | — | $95k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | $15,000 | · | · |
| 2024–2025 | $80,000 | $80,000 | · |
| 2025–2026 | – | $70,000 | – |
| 2026–2027 | · | $300,000 | – |
| 2027–2028 | · | · | $1,000,000 |
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2028–2029
Capital Works Program (PDF) - 2025–2026Listed at $1M over three years
Capital Works Program (PDF) - 2024–2025Listed at $450k over three years
Capital Works Program (PDF) - 2023–2024Listed at $95k over three years
Capital Works Program (PDF)
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).