Bergins Hill Road Drainage Channel Rehabilitation

What's Being Planned · Suburb: Bundamba · Ref: INF04968 · Last updated: 2026-08-19

Description

Council is planning rehabilitation of the existing stormwater drainage channel on Bergins Hill Road Bundamba.

Status

Construction timing will be dependent on funding in future Council budgets.

What to expect

Currently in design phase

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗

Funded in 2028–2029 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗

2025–20262026–20272027–20283 Year Total
$1M$1M

Capital Works Program 2024–2027 (2024–2025 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗

2024–20252025–20262026–20273 Year Total
$80k$70k$300k$450k

Capital Works Program 2023–2026 (2023–2024 budget · Drainage Rehabilitation · as “Bergins Hill Road Drainage Channel Rehabilitation”) Council source ↗

2023–20242024–20252025–20263 Year Total
$15k$80k$95k

Funding, as published in each program

Financial year2023–2024 program2024–2025 program2025–2026 program
2023–2024$15,000··
2024–2025$80,000$80,000·
2025–2026$70,000
2026–2027·$300,000
2027–2028··$1,000,000

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).