East Ipswich Catchment Drainage Rehabilitation Stage 4
Description
Ipswich City Council is planning to rehabilitate existing stormwater drainage infrastructure within the East Ipswich Catchment, as part of the East Ipswich Catchment Drainage Rehabilitation Project - Stage 4.
Status
This project is currently in the design stage and construction is anticipated to commence in the 2028 - 2029 financial year, subject to Council's budget process.
What to expect
Currently in design phase
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Drainage Rehabilitation · as “East Ipswich Catchment Drainage Rehabilitation Stage 4”) Council source ↗
Funded in 2026–2027, 2027–2028 and 2028–2029 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Drainage Rehabilitation · as “East Ipswich Catchment Drainage Rehabilitation – Stage 4”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| — | $90k | $110k | $200k |
Capital Works Program 2024–2027 (2024–2025 budget · Drainage Rehabilitation · as “East Ipswich Catchment Drainage Rehabilitation – Stage 4”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| — | — | $120k | $120k |
Funding, as published in each program
| Financial year | 2024–2025 program | 2025–2026 program |
|---|---|---|
| 2024–2025 | – | · |
| 2025–2026 | – | – |
| 2026–2027 revised | $120,000 | $90,000 |
| 2027–2028 | · | $110,000 |
Council published different figures for 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027, 2027–2028, 2028–2029
Capital Works Program (PDF) - 2025–2026Listed at $200k over three years
Capital Works Program (PDF) - 2024–2025Listed at $120k over three years
Capital Works Program (PDF) - 2024-06-27Council’s 2024-2025 Annual Plan and Budget forges path for future growth
Ipswich First
In the news (1)
| Article | Date | Source |
|---|---|---|
| Council’s 2024-2025 Annual Plan and Budget forges path for future growth | 2024-06-27 | Source ↗ |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).