HomeProjects › Woogaroo Closed Landfill Leachate and Gas Management

Woogaroo Closed Landfill Leachate and Gas Management

Current Program · Suburb: Goodna · Ref: INF04475 · Last updated: 2026-08-19

Description

Council is installing leachate and gas management infrastructure at the Woogaroo Closed Landfill site, Goodna

Status

Preliminary works commenced in April 2026 and have been put on hold. Further information and updates will be provided to the community in the coming months.

What to expect

You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Disturbed Land Management · as “Woogaroo Closed Landfill Leachate and Gas Management”) Council source ↗

Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Disturbed Land Management · as “Woogaroo Closed Landfill Leachate and Gas Management”) Council source ↗

2025–20262026–20272027–20283 Year Total
$1.3M$1.3M

Capital Works Program 2024–2027 (2024–2025 budget · Disturbed Land Management · as “Woogaroo Closed Landfill Leachate and Gas Management”) Council source ↗

2024–20252025–20262026–20273 Year Total
$100k$100k

Capital Works Program 2023–2026 (2023–2024 budget · Disturbed Land Management · as “Woogaroo Closed Landfill Leachate and Gas Management”) Council source ↗

2023–20242024–20252025–20263 Year Total
$100k$100k

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).