Home › Projects › Augusta Parkway Road Rehabilitation
Augusta Parkway Road Rehabilitation
Description
Council is undertaking road pavement reconstruction works on a section of Augusta Parkway (Santa Monica Drive to Tournament Drive/Mount Juillerate Drive Roundabout) in Brookwater.
Status
Construction is anticipated to commence in mid-September 2026. Works will be completed at night, Sunday to Thursday between 7pm and 5am. Please follow the direction of traffic control.
What to expect
Night works, changed traffic conditions, detours, slight delays, traffic control, sections of the footpath will be unavailable, increase in noise from machinery
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Sealed Road Rehabilitation · as “Augusta Parkway Road Rehabilitation”) Council source ↗
Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Sealed Road Rehabilitation · as “Augusta Parkway Road Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $2M | $2.5M | — | $4.5M |
Capital Works Program 2024–2027 (2024–2025 budget · Sealed Road Rehabilitation · as “Augusta Parkway Road Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $120k | $2.3M | $2M | $4.4M |
Capital Works Program 2023–2026 (2023–2024 budget · Sealed Road Rehabilitation · as “Augusta Parkway Road Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | $80k | $950k | $1M |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 revised | $80,000 | $120,000 | · |
| 2025–2026 revised | $950,000 | $2,300,000 | $2,000,000 |
| 2026–2027 revised | · | $2,000,000 | $2,500,000 |
| 2027–2028 | · | · | – |
Council published different figures for 2024–2025, 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027
Capital Works Program (PDF) - 2025–2026Listed at $4.5M over three years
Capital Works Program (PDF) - 2024–2025Listed at $4.4M over three years
Capital Works Program (PDF) - 2023–2024Listed at $1M over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 17.3. Notice of Motion - Funding for Installation of traffic lights - Augustine Heights/Brookwater | Tournament Drive | Council — 2025-10-30 |
| 3.1 New Item (Committees) - MATTER ON NOTICE - STATUS OF TREES - ROUNDABOUT AT TOURNAMENT DRIVE/AUGUST PARKWAY | Tournament Drive | Growth Infrastructure and Waste Committee — 2021-11-04 |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).