Description
Council is planning road pavement reconstruction works on Gladstone Road between 23 Gladstone Road and Tiger St, Sadliers Crossing.
Status
This project currently in concept design phase in the 2025-2026FY, with the detail design proposed in 2026-2027FY dependent on funding in future Council budgets.
What to expect
Increase of noise from machinery
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Kerb and Channel Rehabilitation · as “Gladstone Road Kerb and Channel Rehabilitation”) Council source ↗
Funded in 2026–2027, 2027–2028 and 2028–2029 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Kerb and Channel Rehabilitation · as “Gladstone Road Kerb and Channel Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $60k | $60k | — | $120k |
Capital Works Program 2024–2027 (2024–2025 budget · Kerb and Channel Rehabilitation · as “Gladstone Road Kerb and Channel Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| — | $50k | $50k | $100k |
Capital Works Program 2023–2026 (2023–2024 budget · Kerb and Channel Rehabilitation · as “Gladstone Road Kerb and Channel Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | — | $35k | $35k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 | – | – | · |
| 2025–2026 revised | $35,000 | $50,000 | $60,000 |
| 2026–2027 revised | · | $50,000 | $60,000 |
| 2027–2028 | · | · | – |
Council published different figures for 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027, 2027–2028, 2028–2029
Capital Works Program (PDF) - 2025–2026Listed at $120k over three years
Capital Works Program (PDF) - 2024–2025Listed at $100k over three years
Capital Works Program (PDF) - 2023–2024Listed at $35k over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 16.2. Provisional Projects Approval | Gladstone Road | Council — 2023-12-07 |
| 15. Surrender and Acquisition of Drainage Easements for INF02666 Over 82 and 84 Gladstone Road, Coalfalls | Gladstone Road | Governance and Transparency Committee — 2023-03-09 |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).