Home › Projects › Parcell and Holt Street Drainage Improvements
Parcell and Holt Street Drainage Improvements
Description
Council is planning to undertake stormwater drainage improvements at the Brassall Grove Unit Complex on Parcell Street, Brassall.
Status
Design has been completed with construction expected in the 2026-2027 financial year.
What to expect
Increase of noise from machinery. Traffic control. Partial lane closure
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗
Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2024–2027 (2024–2025 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $680k | — | — | $680k |
Capital Works Program 2023–2026 (2023–2024 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| $600k | — | — | $600k |
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027
Capital Works Program (PDF) - 2024–2025Listed at $680k over three years
Capital Works Program (PDF) - 2023–2024Listed at $600k over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 15.2. Report of Governance and Transparency Committee No. 2024(01) of 1 February 2024 | Parcell Street | Council — 2024-02-15 |
| 2. Acquisition of Drainage Easement for INF04308 - 13 Parcell Street, Brassall | Parcell Street | Governance and Transparency Committee — 2024-02-01 |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).