Council is planning to undertake stormwater drainage improvements at the Brassall Grove Unit Complex on Parcell Street, Brassall.

Status

Design has been completed with construction expected in the 2026-2027 financial year.

What to expect

Increase of noise from machinery. Traffic control. Partial lane closure

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗

Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2024–2027 (2024–2025 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗

2024–20252025–20262026–20273 Year Total
$680k$680k

Capital Works Program 2023–2026 (2023–2024 budget · Local Drainage · as “Parcell and Holt Street Drainage Improvements”) Council source ↗

2023–20242024–20252025–20263 Year Total
$600k$600k

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Meeting items mentioning this project's streets

ItemStreetMeeting
15.2. Report of Governance and Transparency Committee No. 2024(01) of 1 February 2024Parcell StreetCouncil — 2024-02-15