Under Construction · Suburb: Ipswich · Ref: INF05367 · Last updated: 2026-10-28

Description

Ipswich City Council is restoring the existing sunken basement floor at the Ipswich Soldiers RSL Memorial Hall.

Status

Construction is commencing on Monday, 2 November 2026 and is anticipated to be completed by mid- March 2027.

What to expect

Increase of noise from machinery. Traffic control. Partial lane closure

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Facility Rehabilitation · as “Ipswich RSL Floor Levels Refurbishment”) Council source ↗

Funded in 2026–2027 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Facility Rehabilitation · as “Ipswich RSL Floor Levels Refurbishment”) Council source ↗

2025–20262026–20272027–20283 Year Total
$150k$100k—$250k

Capital Works Program 2024–2027 (2024–2025 budget · Facility Rehabilitation · as “Ipswich RSL Floor Levels Refurbishment”) Council source ↗

2024–20252025–20262026–20273 Year Total
—$50k$300k$350k

Funding, as published in each program

Financial year2024–2025 program2025–2026 program
2024–2025–·
2025–2026 revised$50,000$150,000
2026–2027 revised$300,000$100,000
2027–2028·–

Council published different figures for 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).