York Street Kerb and Channel Rehabilitation

Historic · Suburb: East Ipswich · Ref: INF04293 · Last updated: 2026-08-19

Description

Council reconstructed a section of kerb and channel on York Street (between no. 8 and 10), East Ipswich

Status

This project was completed late May 2025.

What to expect

You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery

Funding (Capital Works Program)

Capital Works Program 2025–2028 (2025–2026 budget · Kerb and Channel Rehabilitation · as “York Street Kerb and Channel Rehabilitation”) Council source ↗

2025–20262026–20272027–20283 Year Total
$140k$140k

Capital Works Program 2024–2027 (2024–2025 budget · Kerb and Channel Rehabilitation · as “York Street Kerb and Channel Rehabilitation”) Council source ↗

2024–20252025–20262026–20273 Year Total
$40k$350k$390k

Capital Works Program 2023–2026 (2023–2024 budget · Kerb and Channel Rehabilitation · as “York Street Kerb and Channel Rehabilitation”) Council source ↗

2023–20242024–20252025–20263 Year Total
$20k$25k$45k

Funding, as published in each program

Financial year2023–2024 program2024–2025 program2025–2026 program
2023–2024$20,000··
2024–2025 revised$25,000$40,000·
2025–2026 revised$350,000$140,000
2026–2027·
2027–2028··

Council published different figures for 2024–2025, 2025–2026 in different programs. Both are Council's own; each links to the page it appears on.

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).