Council has undertaken culvert rehabilitation works on Railway Street, Rosewood.
Status
Construction was completed in June 2026.
What to expect
Increase of noise from machinery
Funding (Capital Works Program)
Capital Works Program 2025–2028 (2025–2026 budget · Bridge and Culvert Rehabilitation · as “Railway Street Stormwater Drainage Relining”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $153k | — | — | $153k |
Capital Works Program 2024–2027 (2024–2025 budget · Bridge and Culvert Rehabilitation · as “Railway Street Stormwater Drainage Relining”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $40k | — | — | $40k |
Capital Works Program 2023–2026 (2023–2024 budget · Bridge and Culvert Rehabilitation · as “Railway Street Stormwater Drainage Relining”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | $40k | — | $40k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 | $40,000 | $40,000 | · |
| 2025–2026 | – | – | $153,000 |
| 2026–2027 | · | – | – |
| 2027–2028 | · | · | – |
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2025–2026Listed at $153k over three years
Capital Works Program (PDF) - 2024–2025Listed at $40k over three years
Capital Works Program (PDF) - 2023–2024Listed at $40k over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 6 New Trustee Lease over Rosewood Showgrounds, 1 Railway Street, Rosewood | Railway Street | Council — 2026-08-27 |
| 6. New Trustee Lease over Rosewood Showgrounds, 1 Railway Street, Rosewood | Railway Street | Finance and Governance Committee — 2026-08-11 |
| 14.3. Lease for Renewal Over Trust Land - Rosewood Showgrounds - 1 Railway Street Rosewood | Railway Street | Council — 2024-01-25 |
| 15.2. Report of Governance and Transparency Committee No. 2023(11) of 28 November 2023 | Railway Street | Council — 2023-12-07 |
| 16.2. Provisional Projects Approval | Railway Street | Council — 2023-12-07 |
| 3. Leases for Renewal over Trust Land - Queens Park Tennis Facility - 76 Chermside Road Ipswich, and Rosewood Showgrounds (the "Green Shed") - 1 Railway Street Rosewood | Railway Street | Governance and Transparency Committee — 2023-11-28 |
| 16.7. Procurement - Rosewood Showgrounds Camping Facility | Railway Street | Council — 2022-01-27 |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).