HomeProjects › Alfred Street Kerb and Channel

Alfred Street Kerb and Channel

What's Being Planned · Suburb: Riverview · Ref: INF04668 · Last updated: 2026-08-19

Description

Council is planning the installation of kerb and channel on Alfred Street, Riverview, from 53 Alfred Street to its western end.

Status

The project design is complete. Construction is dependent on funding in future Council budgets.

What to expect

Increase of noise from machinery. Traffic control. Partial lane closure

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Kerb and Channel · as “Alfred Street Kerb and Channel”) Council source ↗

Funded in 2027–2028 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Kerb and Channel · as “Alfred Street Kerb and Channel”) Council source ↗

2025–20262026–20272027–20283 Year Total
$40k$40k

Capital Works Program 2024–2027 (2024–2025 budget · Kerb and Channel · as “Alfred Street Kerb and Channel”) Council source ↗

2024–20252025–20262026–20273 Year Total
$40k$220k$260k

Capital Works Program 2023–2026 (2023–2024 budget · Kerb and Channel · as “Alfred Street Kerb and Channel”) Council source ↗

2023–20242024–20252025–20263 Year Total
$115k$115k

Funding, as published in each program

Financial year2023–2024 program2024–2025 program2025–2026 program
2023–2024··
2024–2025·
2025–2026 revised$115,000$40,000$40,000
2026–2027·$220,000
2027–2028··

Council published different figures for 2025–2026 in different programs. Both are Council's own; each links to the page it appears on.

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Source: Ipswich City Council Civic Projects Map (CC BY 4.0).