Home › Projects › Taloma Avenue Road Rehabilitation
Taloma Avenue Road Rehabilitation
Description
Council is planning road pavement reconstruction works on Taloma Avenue between Lansdowne Way and Blackall Street, Chuwar.
Status
This project has concept design completed and is expected to move into the detailed design phase within the next two years. Construction timing will be dependent on funding in future Council budgets.
What to expect
Currently in design phase
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Sealed Road Rehabilitation · as “Taloma Avenue Road Rehabilitation”) Council source ↗
Funded in 2027–2028 and 2028–2029 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Sealed Road Rehabilitation · as “Taloma Avenue Road Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $55k | $70k | — | $125k |
Capital Works Program 2024–2027 (2024–2025 budget · Sealed Road Rehabilitation · as “Taloma Avenue Road Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| — | $55k | $55k | $110k |
Capital Works Program 2023–2026 (2023–2024 budget · Sealed Road Rehabilitation · as “Taloma Avenue Road Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | — | $20k | $20k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 | – | – | · |
| 2025–2026 revised | $20,000 | $55,000 | $55,000 |
| 2026–2027 revised | · | $55,000 | $70,000 |
| 2027–2028 | · | · | – |
Council published different figures for 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2027–2028, 2028–2029
Capital Works Program (PDF) - 2025–2026Listed at $125k over three years
Capital Works Program (PDF) - 2024–2025Listed at $110k over three years
Capital Works Program (PDF) - 2023–2024Listed at $20k over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 5. Acquisition of Drainage Easement INF04249 - 11 Panton Street, Woodend | Blackall Street | Growth Infrastructure and Waste Committee — 2021-11-04 |
| 6. Acquisition of Drainage Easement INF04251 - 50 Blackall Street, East Ipswich | Blackall Street | Growth Infrastructure and Waste Committee — 2021-11-04 |
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).