Historic · Suburb: Goodna · Ref: INF05141 · Last updated: 2026-08-19

Description

Council undertook culvert rehabilitation works on Lower William Street, Goodna.

Status

Construction was completed in August 2025.

What to expect

Increase of noise from machinery

Funding (Capital Works Program)

Capital Works Program 2024–2027 (2024–2025 budget · Bridge and Culvert Rehabilitation · as “Lower William Street Stormwater Drainage Relining”) Council source ↗

2024–20252025–20262026–20273 Year Total
$90k$90k

Capital Works Program 2023–2026 (2023–2024 budget · Bridge and Culvert Rehabilitation · as “Lower William Street Stormwater Drainage Relining”) Council source ↗

2023–20242024–20252025–20263 Year Total
$90k$90k

Funding, as published in each program

Financial year2023–2024 program2024–2025 program
2023–2024·
2024–2025$90,000$90,000
2025–2026
2026–2027·

· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.