Home › Projects › Mary Street Road Rehabilitation
Mary Street Road Rehabilitation
Description
Council is planning road pavement reconstruction works on Mary Street (between Thomas St to Cunningham Hwy bridge), Blackstone.
Status
The project is nearing concept design completion, with detail design scheduled to be undertaken in 2026-2027 financial year. Construction timing is dependent on funding in future Council budgets.
What to expect
You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery
Funding (Capital Works Program)
Capital Works Program 2026–2029 (2026–2027 budget · Sealed Road Rehabilitation · as “Mary Street Road Rehabilitation”) Council source ↗
Funded in 2026–2027, 2027–2028 and 2028–2029 — per-project amounts not published in the 2026–2027 program.
Capital Works Program 2025–2028 (2025–2026 budget · Sealed Road Rehabilitation · as “Mary Street Road Rehabilitation”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $70k | $130k | $100k | $300k |
Capital Works Program 2024–2027 (2024–2025 budget · Sealed Road Rehabilitation · as “Mary Street Road Rehabilitation”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| — | $70k | $70k | $140k |
Capital Works Program 2023–2026 (2023–2024 budget · Sealed Road Rehabilitation · as “Mary Street Road Rehabilitation”) Council source ↗
| 2023–2024 | 2024–2025 | 2025–2026 | 3 Year Total |
|---|---|---|---|
| — | $50k | $50k | $100k |
Funding, as published in each program
| Financial year | 2023–2024 program | 2024–2025 program | 2025–2026 program |
|---|---|---|---|
| 2023–2024 | – | · | · |
| 2024–2025 | $50,000 | – | · |
| 2025–2026 revised | $50,000 | $70,000 | $70,000 |
| 2026–2027 revised | · | $70,000 | $130,000 |
| 2027–2028 | · | · | $100,000 |
Council published different figures for 2025–2026, 2026–2027 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2026–2027Listed as funded in 2026–2027, 2027–2028, 2028–2029
Capital Works Program (PDF) - 2025–2026Listed at $300k over three years
Capital Works Program (PDF) - 2024–2025Listed at $140k over three years
Capital Works Program (PDF) - 2023–2024Listed at $100k over three years
Capital Works Program (PDF)
Meeting items mentioning this project's streets
| Item | Street | Meeting |
|---|---|---|
| 4. Asset and Infrastructure Services Department Capital Delivery Report July 2026 | Cunningham Highway | Infrastructure, Planning and Assets Committee — 2026-09-15 |
| 2 Response to Notice of Motion - Intersections of Law Street / Byrne Street / Mary Street and Law Street / Bognuda Street, Bundamba | Mary Street | Council — 2026-06-25 |
| 2. Response to Notice of Motion - Intersections of Law Street / Byrne Street / Mary Street and Law Street / Bognuda Street, Bundamba | Mary Street | Infrastructure, Planning and Assets Committee — 2026-06-16 |
| 1. TMR Briefing to Councillors | Cunningham Highway | Councillor Briefing and Workshop Session — 2026-02-10 |
| 3 Amendment of Council Resolutions for Proposed Acquisitions of Land for Ripley and Fischer Road Upgrades | Cunningham Highway | Council — 2025-09-25 |
| 3. Amendment of Council Resolutions for Proposed Acquisitions of Land for Ripley and Fischer Road Upgrades | Cunningham Highway | Finance and Governance Committee — 2025-09-16 |
| 16.3. Motions for 2025 Local Government Association of Queensland Conference | Cunningham Highway | Council — 2025-07-30 |
| 4. Greenwood Village Road and Redbank Plains Road intersection | Cunningham Highway | Councillor Briefing and Workshop Session — 2025-06-17 |
| 9. 5356 Ripley Road and Fischer Road Upgrade - Design & Construct | Cunningham Highway | Finance and Governance Committee — 2024-12-03 |
| 6 Procurement: Variation to Contract 16456 Prorgram Partner for the Ipswich Centre CBD Transformation | Cunningham Highway | Council — 2024-10-24 |
| 7 Proposed Acquisitions of Land for INF04658 Ripley Road Upgrade - Cunningham Highway to Fischer Road | Cunningham Highway | Council — 2024-10-24 |
| 17.1. Notice of Motion - Update to Meeting Procedures Policy | Cunningham Highway | Council — 2024-10-24 |
| 7. Proposed Acquisitions of Land for INF04658 Ripley Road Upgrade - Cunningham Highway to Fischer Road | Cunningham Highway | Finance and Governance Committee — 2024-10-15 |
| 13.2. Interim Safety Measures be Investigated for the area surrounding the Amberley Intersection, Cunningham Highway | Cunningham Highway | Council — 2024-08-22 |
| 10 New Item (Council) - Matters of Public Interest | Cunningham Highway | Council — 2022-12-08 |
Showing the 15 most recent of 24 — see the street pages above for the rest.
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).