HomeProjects › River Road Road Rehabilitation

River Road Road Rehabilitation

What's Being Planned · Suburb: Redbank · Ref: INF02768 · Last updated: 2026-08-19

Description

Council is planning road pavement reconstruction works on a section of River Road, Redbank.

Status

This project is currently in the detail design phase, with preliminary works (utility service relocations) expected to be undertaken in the 2026-2027FY and 2027-2028 financial years. Construction timing is dependent on funding in future Council budgets

What to expect

You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery

Funding (Capital Works Program)

Capital Works Program 2026–2029 (2026–2027 budget · Sealed Road Rehabilitation · as “River Road Rehabilitation”) Council source ↗

Funded in 2026–2027, 2027–2028 and 2028–2029 — per-project amounts not published in the 2026–2027 program.

Capital Works Program 2025–2028 (2025–2026 budget · Sealed Road Rehabilitation · as “River Road Rehabilitation”) Council source ↗

2025–20262026–20272027–20283 Year Total
$220k$600k$480k$1.3M

Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.

Timeline

Everything Council has published about this project, newest first. Each entry links to its source.

Meeting items mentioning this project's streets

ItemStreetMeeting
2. Response to Petition - Opening of River Road, Bundamba to traffic at its intersection with Nelson StreetRiver RoadGrowth Infrastructure and Waste Committee — 2022-08-11
7.2. Petition - Opening of River Road Bundamba to traffic at Nelson StreetRiver RoadCouncil — 2022-04-21