Home › Projects › Thagoona Haigslea Road Footpath
Thagoona Haigslea Road Footpath
Description
Council installed new footpath on Thagoona Haigslea Road, along the property frontage of Haigslea State School. This project was part of the School Transport Infrastructure Program.
Status
Construction was completed in the 2025-2026 financial year.
What to expect
You may experience changed traffic conditions, delays in access in and out of properties, road closures, detours, slight delays, traffic control, some night works as necessary and an increase in noise from machinery
Funding (Capital Works Program)
Capital Works Program 2025–2028 (2025–2026 budget · Road Safety and Operations · as “Thagoona Haigslea Road Footpath”) Council source ↗
| 2025–2026 | 2026–2027 | 2027–2028 | 3 Year Total |
|---|---|---|---|
| $120k | — | — | $120k |
Capital Works Program 2024–2027 (2024–2025 budget · Road Safety and Operations · as “Thagoona Haigslea Road Footpath”) Council source ↗
| 2024–2025 | 2025–2026 | 2026–2027 | 3 Year Total |
|---|---|---|---|
| $20k | $177k | — | $197k |
Funding, as published in each program
| Financial year | 2024–2025 program | 2025–2026 program |
|---|---|---|
| 2024–2025 | $20,000 | · |
| 2025–2026 revised | $177,000 | $120,000 |
| 2026–2027 | – | – |
| 2027–2028 | · | – |
Council published different figures for 2025–2026 in different programs. Both are Council's own; each links to the page it appears on.
· = outside that program's three-year window (not zero). Amounts are Council's, in the year they were published for.
Amounts are as published in Council's Capital Works Program PDFs ($'000, multiplied out). See all capital works programs.
Timeline
Everything Council has published about this project, newest first. Each entry links to its source.
- 2025–2026Listed at $120k over three years
Capital Works Program (PDF) - 2024–2025Listed at $197k over three years
Capital Works Program (PDF)
Source: Ipswich City Council Civic Projects Map (CC BY 4.0).